Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
resourcing the new economy for a better tomorrow
EQ Resources Limited
Quarterly Activities Report
Quarter ended 31st March 2025
HIGHLIGHTS
SALORO OPERATIONS
•
Phase 5 Pit produced 342,877 t of ore @ 0.188 % WO₃ (strip ratio 4.6:1) while deepening the south pit.
•
Phase 6 Pit pre-stripping advanced to the 690 RL in the north; Phase 7 Pit eastern ramps commenced.
•
Crushing-plant initiatives lifted hourly throughput from 200 t/h (Jan 2024) to 290 t/h (Mar 2025); screening
efficiency at 94%.
•
Program of further crushing circuit optimisation, additional jigs/Falcon concentrator and table-circuit
expansion is expected to raise recovery to target level of >70% over coming quarters.
•
Third XRT sorter and wet-screening station ordered; planned start-up Q1FY2026 will add 30–40 kt/month
sorting capacity and cut operating costs.
MT CARBINE OPERATIONS
•
Strong mining performance with 702,265 t total material moved (+23% QoQ) despite wet-season
conditions; blasting volumes hit a post-restart record (603,309 t).
•
Ore deliveries 182,449 t (+48% QoQ); Ore grades remained modest throughout the quarter as rain season
disrupted stripping above Stage 2 Pit outline (accessing high-grade Iolanthe Vein Package); Mining has
reached 335-325 RL, with higher grades expected next quarter.
•
Funding assessment under way for the plant upgrade program that is expected to double processing
capacity; Various potential debt providers conducting due diligence, while Company is waiting feedback
on its grant application from US Department of Defense.
EQR EXPLORATION
•
Soil-sample testing and characterisation for Wolfram Camp, conducted with TOMRA and the University
of Queensland, are awaiting results, and planning has begun for large-scale sampling and ore sorter trials.
FINANCIAL AND CORPORATE**
•
Group cash receipts from customers were A$17.5 million in the quarter.
•
Fastmarkets Ammonium Paratungstate (APT) CIF Rotterdam/Baltimore mid-price of US$385 per mtu* on
30 April 2024.
•
Secured A$4.5 million in funding through Offtake Agreements Prepayments within the quarter; further
Prepayments outstanding, basis a series of long-term agreements signed for both Saloro- and Mt Carbine
operations.
Notes: * 1mtu (metric tonne unit) = 10kg WO3 , **All financial numbers are quoted in Australian dollars unless otherwise stated.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 1
resourcing the new economy for a better tomorrow
EQR GROUP Q3 FY2025 - PRODUCTION SUMMARY
Operations
Mt Carbine
Saloro
EQR Group
Unit
Q2FY2025
Q3FY2025
Q2FY2025
Q3FY2025
Q2FY2025
Q3FY2025
Waste
t
449,436
519,816
1,670,600
1,585,941
2,120,036
2,105,757
Ore
t
123,469
182,449
379,132
342,877
502,601
525,326
Total Tonnes Mined
t
572,905
702,265
2,049,732
1,928,818
2,622,637
2,631,083
W:O
3.6 : 1
2.8 : 1
4.4 : 1
4.6 : 1
4.2 : 1
4:1
Closing Ore Stock
t
10,658
17,520
304,076
316,533
314,734
334,053
Gravity Plant Feed
t
61,240
55,200
227,410
222,444
288,650
277,644
Gravity Plant Grade
%
0.238%
0.196%
0.263%
0.234%
-
-
WO3 Produced*
mtu
9,043
6,717
33,249
29,993
42,292
36,710
Strip Ratio
*Note: Metric Tonnes Unit, 1 mtu = 10kg 100% WO3
For the quarter ended 31 March 2025 (Q3 FY2025), the consolidated EQR Group produced 36,322 mtu of tungsten
concentrate (Mt Carbine 6,717 mtu; Saloro 29,605), and 2.6 million total tonnes mined (Mt Carbine 0.7 million tonnes;
Saloro 1.9 million tonnes).
In Q3 FY2025, Mt Carbine switched to an in-house drilling model while retaining a specialist contractor for blasting.
Combined with last quarter’s move to owner-operator mining, this change delivered a pronounced lift in performance:
-
702,265 tonnes of open-pit material mined (+23% QoQ)
-
603,309 tonnes blasted (+70% QoQ)
Stripping reached the upper zone of the Stage 2 Pit outline. Ore grades remained modest in the south-east as mining is
still above the main high-grade Iolanthe Vein Package. Processing output was constrained by lower ore grade and negative
impacts resulting from the Far-North Queensland flooding, which saw a total of 6 weeks disruption in supplies of key
consumables.
The Saloro’s operations recorded another strong quarter, just short of previous quarter production record:
-
380,109 tonnes crushed (-10% QoQ) and 116,007 tonnes sorted (+27% QoQ)
-
Crushing-plant upgrades lifted sustained throughput from ~200 t/h (Jan 2024) to ~290 t/h (Mar 2025) with
screening efficiency at 94%
-
Gravity-circuit enhancements continued: five quadruple tables rebuilt to double-deck, multideck screen
commissioned, two further table conversions scheduled
Minor reduction in total concentrate output (in mtu) mainly attributable to lower grade feed as compared to previous quarter
and slightly reduced plant availability, given the ongoing optimisation and rebuild works. Both metrics are expected to
improve in the coming quarter, with a further capacity expansion realised with the installation of the third XRT Sorter and
integrated wet-screening station in late summer 2025.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 2
resourcing the new economy for a better tomorrow
HEALTH & SAFETY
Saloro Operations
Saloro recorded a modest increase in its lost-time injury frequency rate (LTIFR) from last quarter’s end; nevertheless, the
figure remains well below the Spanish mining-industry benchmark. Other safety indicators improved markedly. Job-Safety
Risk Assessments (“Take 5s”) totalled 1,641 for the quarter—more than double the 765 completed in Q2—with March
alone 173% above the six-month average. The Safety team has conducted 3,617 alcohol test and 34 drug tests in the last
quarter keeping strict safety standards. To sustain this momentum, the team at Saloro will begin reporting statistics by
department and will step-up procedure reviews, training, and workplace inspections.
Around 23 employees also completed a two-part firefighting course. The classroom module covered fire behaviour,
response protocols, and extinguisher selection, while the practical session required participants to navigate a smoke-filled
cabin and extinguish controlled fires. This training ensures personnel are equipped to manage fire incidents both on site
and in everyday settings.
Mt Carbine Operations
83
90
79
80
70
60
60
64
52
50
42
45
67
66
49
61
60
48
47
74
74
49
49
25
25
67
63
50
54
51
46
54
38
40
29
30
19
20
14
18
21
18
25
17
13
13
13
10
-
LTIFR
TRIFR
Average QLD Quarries (LTIFR)
MTIFR
Average QLD Quarries (TRIFR)
At Mt Carbine, five recordable incidents were logged in Q3 FY2025 - one less than in Q2 - reflecting continued emphasis
on proactive safety measures. Alcohol and drug-testing remained rigorous, with 4,697 breath-analysis tests and 36 drug
screens completed during the quarter. The site’s elected Site Safety and Health Representative (SSHR) maintained regular
consultation with the workforce to ensure prompt, transparent resolution of safety concerns and to gauge perceptions of
workplace risk.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 3
resourcing the new economy for a better tomorrow
Additional initiatives strengthened the safety culture:
-
Weekly “lessons-learned” bulletins circulated by the Safety Team summarised relevant incident reports issued by
Resources Safety & Health Queensland (RSHQ).
-
Twenty-nine safety procedures were either introduced or formally reviewed, and twenty-one employees
completed in-house machinery-operation training.
-
“Take 5” personal risk assessments increased to 4,102 for the quarter, demonstrating higher worker engagement
in hazard identification.
Collectively, these actions support the site’s objective of reducing incidents while deepening a culture of shared
responsibility for health and safety.
SALORO OPERATIONS
Open Cut Mining
Picture above: The Barruecopardo Mine Open Pit as at March 2025 looking north, with ongoing progressive rehabilitation
of the waste dumps near the water dams on the front left.
During Q3 FY2025, in addition to achieving the corresponding production targets, the Operational Team at the
Barruecopardo Mine focused on deepening the southern area of the pit as part of the Phase 5 Pit design. Waste stripping
continued in Phase 6 Pit outline, and the pushback of Phase 7 Pit outline in the northern area was initiated.
Ore production in Phase 5 Pit of the Barruecopardo Mine
During the Q3 FY2025, mineral production activities have continued in the current Phase 5 Pit and have focused on the
central and southern areas of the mine, between levels 575 reduced level (RL) and 565 RL. A total of 342,877 tonnes of
Tungsten-bearing ore with an average grade of 0.188% WO3 have been extracted in the quarter. A total of 1.59 million
tonnes of waste were extracted from the pit during the Q3 for a strip ratio of 4.6:1. The slight reduction in mining output
versus the previous quarter reflects a safety-related short pauses in bottom-of-pit mining operations while Phase 6 prestripping advanced in the northern sector.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 4
resourcing the new economy for a better tomorrow
Picture above: The ore production zone during Q3 FY2025 in the Southern Area as per Resource Block Model.
Colours represent the grade of the ore. Red for high grade (>0.15% WO 3). Orange for lower grade (0.07-0.15%
WO3). Blue for very low grade. (0.055-0.07% WO3).
Development of the Barruecopardo Mine Phase 6 Pit, North Area
Picture above: Northern area of Phase 6 Pit at level 700 RL looking South, including the access ramp and bench at level
690 RL, with ore stockpile on the front left and waste dump at the back as of the end of March 2025.
Works in Phase 6 Pit outline have progressed steadily, with the north area brought down to level 700 RL and operations
initiated at the 690 RL, including the construction of the access ramp. These activities have impacted the normal
advancement at the bottom of the pit due to material collapse at the level 625 RL curve. This event was foreseen in the
operational planning, and sufficient ore was stockpiled ahead of the processing plant ensuring uninterrupted feed to
mitigate the short-term halt of mining operations at the bottom of pit. Tungsten deposits at Mt Carbine and Barruecopardo
both consists of sheeted veins, and the open-pit design is aligned to track their continuity. As mining progress deeper, ore
grades are anticipated to rise.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 5
resourcing the new economy for a better tomorrow
Pictured: The Northern Area. Work done in Phase 6 Pit outline, during Q3. The green sections represent the area
mined in January 2025, blue in February and red in March.
Picture above: The Northern Area as of 31st March 2025. Resources Block Model in Phase 6 Pit outline showing
ore block already extracted. Colours represent the grade of the ore. Red for high grade (>0.15% WO3). Orange for
lower grade (0.07-0.15% WO3). Blue for very low grade. (0.055-0.07% WO3).
Quarterly Activities Report - Quarter ended 31st March 2025
Page 6
resourcing the new economy for a better tomorrow
Start of Open Pit Phase 7, with the development of connection ramps.
Picture above: The Eastern pit slope of the Barruecopardo Open Pit , blue arrows showing the ramps in Phase 7.
The east ramps for Phase 7 Pit outline have been initiated, which will connect the eastern slope with the access ramps
from Phase 5 and Phase 6 leading to the waste dump.
Processing
During Q3 FY2025, 380,109 tonnes of ore were fed to the primary crusher - 10 % below the record volume achieved in the
previous quarter. Of this total, 116,007 tonnes were processed through the Ore Sorter Plant, a 27% increase quarter on
quarter.
Production output has had a small 11% decline versus the previous quarter owing to slightly lower ore grade in the current
area mined compared to last quarter, intermittent crusher performance and the under-performance of the legacy quadruple
tables prior to their upgrade. Nevertheless, a total of 26 customer shipments were completed in the quarter, totalling 29,657
mtu of tungsten concentrate.
To improve run-of-mine (ROM) stockpile management, the Operational Team at Saloro, in collaboration with the mining
contractor, have introduced several pro-active actions:
-
Stockpiles have been repositioned closer to the ROM pad, shortening haul distances and improving efficiency.
-
New handling protocols now prevent excessive compaction, while oversize material is removed directly at the
loading faces to reduce downstream blockages.
-
Direct access from the control cabin to both crusher chambers has been enabled, allowing quicker intervention.
In addition
-
Controlled blending of stored scalping material, with the primary crusher feed has begun and will continue during
ore-sorting campaigns to stabilise feed quality and throughput.
Thanks to these initiatives the Crushing Plant throughput rose from around 200 tonnes per hour in January 2024 to 290
tonnes per hour at the end of March 2025.
At the Gravity Plant, notable circuit upgrades progressed during the quarter. High-performance Holman-Wilfley single
shaking tables are being converted to double decks to expand the recovery circuit. Legacy low-cost quadruple tables have
already been replaced in-house as double-deck units, and conversions of WT 505 A and WT 505 B are scheduled. A newly
commissioned multideck screen is operating to specification, achieving screening efficiencies of 94%.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 7
resourcing the new economy for a better tomorrow
Work Program for Upcoming Quarters
In an effort to improve recovery further and enhance performance, the following actions have been scheduled and listed
below. Collectively, these measures are expected to lift throughput, head grade, and overall metal output, delivering an
anticipated overall recovery rate of >70% once implemented.
Crushing Optimisation: A new grizzly is being engineered to regulate feed size to the jaw crusher, paired with a new
monitoring system for stable operation. Roll crusher implementation is planned to reduce fines generation and optimise
particle size.
Throughput Increase: Process adjustments and equipment reconfiguration will correct inefficiencies in the crushing
section, aligning equipment operation with its optimal range.
Recovery Improvements: Additional scavenger jigs and a Falcon concentrator will be introduced to capture ultra-fines
and improve total metal recovery. Recommissioned jigs will be used for periodic cleaning of operational jigs.
Table Circuit Expansion: Completion of the final two table conversions are expected to improve stable recovery in the
final gravity circuit.
Workforce Optimisation: Commissioning of auxiliary plant equipment will allow personnel to focus more on recoverycritical areas.
Ore Sorter Plant Upgrades: Third XRT Sorter and Wet Screening Station to Boost Output
The Processing Plant at Saloro will have its processing capabilities expanded by adding a third XRT ore sorter and
upgrading the existing plant infrastructure. This move aims to increase sorting capacity by an additional 30,000 to 40,000
tonnes a month and support further production growth. The new sorter, set for installation in Q1 FY2026, along with a new
wet screening station and a separate feed system for the historic low-grade ore stockpile, will allow handling larger feed
size and improve plant efficiency.
Figure above: Design sketch of the 3rd XRT Ore Sorter hangar and new wet screening station
The benefits of the new wet screening station will be an enhancement of Ore Sorter efficiency by pre-washing and better
feed classification. The screening operation redirects previously misclassified material to the Gravity Plant, avoiding
material misplacement in the Ore Sorter and ensuring higher overall tungsten recoveries for the operations. The separate
feed station will improve the overall availability of the upgraded Ore Sorter Plant, operating independently from the existing
screening circuit and allowing the XRT Sorters to run standalone, providing greater flexibility to the operations. These
upgrades will enhance ore sorting performance, raise recoveries, and reduce operating costs.
ASX Announcement 17th February 2025: Saloro to Expand XRT Sorting Capacity by 50% To Support Further Production
growth.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 8
resourcing the new economy for a better tomorrow
MT CARBINE OPERATIONS
Open Cut Mining
Picture above: Andy White Open Pit at Mt Carbine, looking North-West, as at end of March 2025
Work on the Eastern Cut-back continued throughout Q3 FY2025 under the 1.1 million-tonne stripping program initiated in
September 2024, following completion of Stage I open-pit mining in the previous quarter.
-
702,265 tonnes of open-pit material were extracted, a 23 % quarter-on-quarter increase and 29 % above the pre–
owner-operator quarterly average - an especially strong outcome given that the work was carried out during the
wet-season months.
-
603,309 tonnes of material have been blasted, a strong 70% increase compared to Q2FY2025, following the last
quarter’s switch to in-house drilling and using a blasting contractor, an all-time record since the re-starting of the
open pit operations in July 2023.
-
Ore deliveries totalled 182,449 tonnes for the quarter, a 48% increase on Q2FY2025. Ore grade was modest consistent with mining focused on the upper benches 375-365 RL - but production has now entered the upper
zone of the Stage 2 Pit accessing the high-grade Iolanthe Vein Package.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 9
resourcing the new economy for a better tomorrow
S
E
Picture above: Resources Block Model showing an extract of the ore blocks in the ore body in the South-East. Colours
represent the grade of the ore. Red for high grade (>0.2% WO3). Blue for low grade. (>0.08% - <0.2% WO3).
The Mining Operations have progressed at the level 335-325 RL at the end of April in the South-East with grades expected
to continue rising in the next quarters and in line with the extensive RC drilling performed, ie. around the Iolanthe- and
Johnson Vein Packages. The Iolanthe Vein Package represents the main ore body targeted in the Stage 2 Pit and still
remains mainly under the South side of the current pit outline with more stripping required to make it accessible. Based
on the RC drilling, first ore deliveries from this area are expected in the level 345-335 RL, with high-grade ore delivered
from level 325-315 RL and below.
Picture above: CAT 320 Excavator and Volvo 60 tonnes Articulated Dump trucks in the South Area at level 375-365 RL
Processing
Ore deliveries from the open pit have met the Crushing Plant requirements without significant reliance on the historic lowgrade stockpile. However, head-feed grade remained modest because the mining operations are still in the Stage 2 Pit
stripping phase. The operation therefore prioritised fresh, short-haul pit ore, which is easier to treat. The Ore Sorter Plant
Quarterly Activities Report - Quarter ended 31st March 2025
Page 10
resourcing the new economy for a better tomorrow
processed 103,301 tonnes for the quarter, 5% more than in Q2, yielding nearly 7,000 tonnes of sorter product. Gravity
Plant output totalled 6,717 mtu, constrained by the lower ore grade from the areas current mined as part of the stripping
program.
Funding alternatives are presently under evaluation for a plant upgrade program that will double the processing capacity,
with all equipment of the new Sandvik Crushing Plant already on site, and head grades are projected to strengthen in the
next quarter as mining advances into the deeper, higher-grade benches of the Stage 2 Pit.
Quarry operations
Mt Carbine Quarry continues to strengthen its regional presence through ongoing project support and community
engagement. This quarter, supply of 20mm concrete aggregates to BZ Contractors for the Daintree River project remains
consistent, alongside the continued delivery of approximately 17,000 tonnes of 4.3 road base to Keltone Constructions at
Hurricane Station. The quarry also maintains ongoing product supply to the Mossman Quarry and has recently begun
providing materials to nearby Brooklyn Station part of the Brooklyn Wildlife Sanctuary that contains World Heritage listed
habitats for road maintenance initiatives.
In a proactive step toward local infrastructure development, the quarry has engaged with local ministers and council
representatives regarding the proposed upgrade of Bushy Creek Bridge. Mt Carbine Quarry has committed up to
A$150,000 worth of quarry products to support the project, with formal meetings scheduled for Q4 FY2025 to further
discussions.
FINANCIAL & CORPORATE
Empowering EQR’s Next Phase of Growth Through Strategic Appointments
EQ Resources has expanded its four-year partnership with VISTRA Australia (“Vistra”), appointing the firm to provide CFOadvisory services in addition to the company-secretarial and governance support already delivered by Melanie Leydin. The
Vistra team will be led by Chartered Accountant and Governance Institute Associate Tony Di Pietro, who brings more than
20 years’ finance-leadership experience with ASX-listed companies operating internationally.
CEO Kevin MacNeill has transitioned to Chief Technical Officer (“CTO”) on 1 April 2025. This change allows him to
concentrate on technical improvements at the Saloro and Mt Carbine operations while working reduced hours for personal
reasons. Mr MacNeill, who has steered EQR since 2019, will continue to drive operational excellence and support the
Company’s expansion and M&A pipeline.
Effective the same date, Non-Executive Chairman Oliver Kleinhempel has assumed the role of Executive Chairman until
a new CEO/Managing Director is appointed, after which he will revert to a Non-Executive capacity. Mr Kleinhempel, a key
architect of EQR’s strategy since 2019, will focus on capital management and long-term direction. He has also resigned
as a director of CRONIMET Australia Pty Ltd following that company’s transfer of its Mt Carbine joint-venture interest to
EQR in July 2024.
The Board has welcomed Craig Bradshaw as a Non-Executive Director. Mr Bradshaw brings extensive tungsten-industry
expertise, having served as CEO of Masan High-Tech Materials (operator of the Nui Phao mine and complex in Vietnam)
and as Managing Director of H.C. Starck Tungsten Powders, with facilities in Germany, China and Canada, prior to its sale
to Mitsubishi Materials in December 2024. Earlier roles include senior positions at Mt Isa Mines, MMG’s Sepon operations
and Toll Holdings. A qualified CPA, he holds a Business degree and is a member of FINSIA and AusIMM. The Board views
his deep market insight and operational track record as a significant asset for EQR’s growth agenda.
Finally, David Laulau has been appointed General Manager of the Mining Operations at Mt Carbine. Mr Laulau brings more
than 26 years’ open-pit and underground experience across Papua New Guinea and Australia, managing large workforces
and multimillion-dollar budgets with a strong focus on safety, efficiency and environmental stewardship. He holds a
Bachelor of Mining Engineering from the Papua New Guinea University of Technology and completed postgraduate studies
at Tohoku University, Japan. His addition further bolsters EQR’s senior leadership capability.
Acquisition of Tungsten Metal Group Progressing
The Company has progressed on its proposed acquisition of Tungsten Metals Group (TMG), which operates the largest
ferrotungsten (FeW) plant outside China. Although both parties completed significant due diligence under a binding Heads
of Agreement (HoA) and an exclusivity period ended on 31 January 2025, definitive agreements have yet to be signed.
Discussions remain ongoing, and EQR will keep shareholders informed as they progress. Once finalised, the acquisition
would enable EQR to diversify its product offerings and vertically integrate its tungsten operations, leveraging the TMG
Group’s large-scale, cost-competitive FeW facility.
Quarterly Activities Report - Quarter ended 31st March 2025
Page 11
resourcing the new economy for a better tomorrow
ASX Announcement 14th February 2025: EQR Provides Update to Ferrotungsten Producer Acquisition.
Tungsten Markets
Five Long-Term Contracts Secure EQR’s Global Tungsten Supply
Western buyers have responded to China’s new export-licence regime by locking in multi-year offtake deals that include
sizeable advance payment clauses. Suppliers demand these prepayments to cushion the timing risk of securing export
licences, while buyers value the price visibility and security of supply. In effect, the US-China trade war has nudged the
market away from spot trading and toward relationship-based contracts that stabilise revenue for mining companies and
offer downstream producers a hedge against further policy shocks.
At the same time, geopolitical pressure is accelerating investment in non-Chinese mining and processing capacity. Projects
in Australia, Canada, South Korea and Vietnam have drawn fresh capital, from U.S. Defense Production Act funds to
private equity, aimed at building a fully Western tungsten chain. Western consumers will continue relying on established
suppliers like EQR to fill the supply gap created by Chinese export controls considering that most new mining projects can
face long lead times before any concentrate reaches the market.
Producers such as EQR are moving downstream through acquisitions (e.g., the proposed purchase of Tungsten Metals
Group’s ferrotungsten smelter) so they can capture more value within secure jurisdictions. These shifts, together with a
higher and more volatile APT price, mean inventory now ties up more working capital: processors must finance larger
stocks and meet stricter collateral terms from lenders. Overall, supply-security strategies are reshaping cash-flow patterns
across the tungsten sector, embedding higher fixed commitments but also strengthening non-Chinese resilience.
EQR has entered into five new offtake agreements, worth an estimated US$124 million at current tungsten prices, covering
around 470 containers of 50% WO₃ concentrate from its Australian and Spanish operations. With each contract tied to
Fastmarkets’ APT price, EQR will supply approximately 25% of its production to Europe, 25% to North America, and the
remainder 50% to Asia. These long-term deals come amid growing tungsten demand outside China, driven by recent
Chinese export restrictions. Each agreement includes an advance payment component..
ASX Announcement 19th March 2025: EQR Signs Five Long-Term Offtake Agreements For The Next 24 Months.
Source: Fastmarkets. Tungsten APT 88.5% WO3 min cif Rotterdam and Baltimore duty-free, $/mtu WO3
The APT Mid Price has increased from US$330/mtu at the end of Q2 FY2025 to US$380/mtu at the of Q3 FY2025 recording
a substantial 15% increase Quarter-on-Quarter and a 21% increase Year-on-Year from March 2024. Tungsten shipments
are invoiced and settled in U.S. dollars.
Quarterly cash flow report
Cash flows from operating activities
In Q3 FY2025, net cash used in operating activities totalled A$1.2 million. Pleasingly, the Saloro business generated
positive operating cashflows of A$2.1 million. The positive cashflow generation from Saloro is due to a very strong
production quarter with concentrate production of 33,249 mtu achieved and recoveries consistently above 60%. Mt Carbine
generated negative operating cashflows of A$3.3 million in the quarter due to lower concentrate output, and from changes
Quarterly Activities Report - Quarter ended 31st March 2025
Page 12
resourcing the new economy for a better tomorrow
to the mine plan that is currently focussing on waste stripping works to gain access to the high-grade Iolanthe ore body,
expected to start being mined in the coming quarter.
Cash flows from investing activities
In Q3 FY2025, net cash used in investing activities totalled A$1.6 million. During the quarter, the Company invested a
further A$1.0 million at Mt Carbine, using mine waste to raise the noise & visual bund at the site, which is a requirement
under the Mt Carbine Mining Lease. A further A$0.6 million was dedicated to acquiring plant and equipment.
Cash flows from financing activities
In Q3 FY2025, Net cash from financing activities totalled A$7.7 million.
Cash and financing facilities
As of 31 March 2025, the Company held cash of A$1.9 million, a decrease from A$0.9 million in cash held at 31 December
2024. Spanish loan facilities remained relatively static in Euros, with headroom of A$0.8 million at quarter end.
Payments to related parties of the entity and their associates during the quarter were $107k compromising of Director fees
as outlined in the Appendix 5B. All numbers included in the Quarterly Cash Flow Report are unaudited.
SUSTAINABILITY & SOCIAL PROGRAMS
High-School students visit Mt Carbine
Twenty-four students from St Augustine’s College in Cairns had a site
tour Mt Carbine, rotating through the laboratory, maintenance workshop,
retreatment circuit and open-pit geology stations after an introduction by
Ryan MacNeill and Mick Barry. The visit offered hands-on exposure to
mineral analysis, heavy-equipment maintenance, sustainable resource
recovery and mine geology, sparking strong interest in resources-sector
careers. EQ Resources regards initiatives like this as vital for cultivating
the next generation of talent. By demonstrating how vibrant and
technologically advanced the Australian mining industry has become—
and the breadth of high-quality career paths it offers—the Company helps ensure a skilled workforce for the future while
giving students a tangib