Quarterly Activities Report - Quarter ended 31 March 2026 Page 1
EQ Resources Limited
Quarterly Activities Report
Quarter Ended 31 March 2026
HIGHLIGHTS
TUNGSTEN MARKET STRENGTHENS FURTHER
• Fastmarkets Ammonium Paratungstate (“APT”) CIF Rotterdam/Baltimore low-price was US$2,800 per
mtu* on 31 March 2026, almost +240% increase Quarter-On-Quarter (QoQ) and a +700% increase
Year-On-Year from US$350 on 31 March 2025. The average low price for the quarter was
US$1,874/mtu.
BARRUECOPARDO OPERATIONS IMPACTED BY ADVERSE WEATHER
• Significant adverse weather events impacted operations across the March quarter with Q1 2026
ranking among the wettest first quarters on record at Barruecopardo — almost certainly the wettest
Q1 in the last ~50 years, driven by an exceptional January–February storm train (Spain's wettest 2-
month opening since 1979) that produced ~110% above-normal precipitation in Salamanca province.
March 2026 rainfall was below normal, but this did not materially reverse the Q1 anomaly.
• Operations focused on restoring pit access because of the excessive rainfall, with active work
progressing to re-establish access to the northern bottom of the pit and advance mining through
Phases 6 and 7.
• Mining and processing volumes were reduced quarter-on-quarter as activities prioritised waste
stripping in the North in Phase 6 and pit access restoration, with ore mined reflecting modest grades
at the current mining horizon.
RECORD MATERIAL MOVEMENT AT MT CARBINE DESPITE WET WEATHER
• Access to the Iolanthe vein system delayed due to wet season impacts, with intermittent feed being
sourced late March 2026. This is expected to ramp up from end April.
• Record quarterly material extracted of 821,678 tonnes, supported by continued stripping despite
wet-season impacts on drilling and blasting activities.
• Ore mined increased materially quarter-on-quarter, particularly toward the end of the period, as access
was established to the early stages of the higher-grade Iolanthe vein system.
BALANCE SHEET STRENGTHENING ENABLES PRODUCTION RAMP-UP
• Available cash on hand at 31 March 2026 of A$15.5 million with A$15m in accounts receivable,
positions the company well during the expected production ramp in Q4 FY2026. The Company
continues to believe it has sufficient funds to meet the production ramp up.
• A$32.7m of revenue was generated during the quarter resulting in cash receipts of A$19.8 after
reducing historical prepayments by A$6.9m and A$5.9m increase in accounts receivable.
• Reduced the Spanish debt by €1.5m to €15 million and refinanced this amount over a three-year period
with an interest rate of 1-month Euribor plus 5.5%, being 7.4% at 31 March 2026.
Notes: * 1mtu (metric tonne unit) = 10kg 100% WO3 , **All financial numbers are quoted in Australian dollars unless otherwise stated
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 2
HEALTH, SAFETY & ENVIRONMENT
The 12-Month Lost Time Injury Frequency Rate graph per Million Working Hours
Barruecopardo Operations
Barruecopardo maintained a strong focus on safety performance and workforce engagement during Q3 FY2026, supported
by ongoing safety assurance activities, training and testing programs. During the quarter, a total of 3,775 alcohol tests and
33 drug tests were conducted across the operation, in line with site safety management requirements.
Safety training and awareness activities continued to be actively reinforced. During the quarter 31 safety-related topics
were delivered through regular safety sessions. In addition, 551 Take 5 job safety analyses were completed during the
period, demonstrating continued workforce participation in hazard identification and risk management.
Environmental and safety management remained integrated into daily operations, with a continued emphasis on
maintaining safe access conditions, procedural compliance and proactive risk identification as mining activities progressed
through variable site conditions.
Mt Carbine Operations
During Q3 FY2026, Mt Carbine maintained a strong focus on safety performance while navigating challenging wet-season
conditions and increased operational complexity associated with accelerated mining activities. Safety leadership visibility
was reinforced through increased supervisor engagement; targeted toolbox talks and continued emphasis on hazard
identification and procedural compliance.
Several high-potential incidents and equipment-related events were recorded during the quarter, primarily associated with
mobile equipment interaction and working near infrastructure. These incidents were investigated promptly, with corrective
actions implemented, including tighter access controls, revised clean-up procedures and the increased use of
fit-for-purpose equipment. Where appropriate, disciplinary actions were taken to reinforce expected safety behaviours.
Alcohol and drug testing, “Take 5” participation and safety observations continued throughout the quarter. A total of 5,947
alcohol tests were conducted, alongside ongoing drug testing in line with site safety requirements. Workforce participation
in hazard identification remained high, with 6,016 “Take 5” safety observations completed during the quarter.
Training and competency development continued to support safe operations, with 43 employees completing internal
training sessions and 33 employees undertaking external training during the period. Environmental management and water
stewardship remained a key focus, with pit dewatering, dam monitoring and water-handling procedures actively managed
to maintain compliance during periods of elevated rainfall.
54
49
40
37
29
33
41
36
49 49
40
35
32
16
19
22 22 23 23 23
26
23 23 23
17
20
-
10
20
30
40
50
60
Mt Carbine Barruecopardo LTIFR Mining (Spain)
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 3
EQR GROUP Q3 FY2026 - PRODUCTION SUMMARY
Operations Mt Carbine Barruecopardo EQR Group
Unit
Q2
FY2026
Q3
FY2026
Q2
FY2026
Q3
FY2026
Q2
FY2026
Q3
FY2026
Material blasted t 906,604 582,237 2,748,955 2,556,468 3,655,560 3,138,705
Total Tonnes Mined t 777,873 821,678 2,505,085 2,260,204 3,282,958 3,081,882
Waste mined t 721,290 726,453 2,036,865 2,098,118 2,758,155 2,824,571
Ore mined t 56,583 95,795 468,220 162,086 524,803 257,881
Strip Ratio W:O 12.7 : 1 7.6 : 1 4.4 : 1 12.9 : 1 5.3 : 1 11 : 1
Closing Ore Stock -
Rom
t 70,236 83,785 250,715 123,100 320,951 206,885
Closing Ore Stock - LGS t 9,483,819 9,393,566 9,483,819 9,393,566
Crushing Plant Feed t 157,965 103,345 469,666 413,303 627,631 516,648
Gravity Plant Feed t 64,278 45,239 236,603 218,297 300,881 263,536
Gravity Plant Grade % 0.126% 0.140% 0.236% 0.162% - -
Recovery % 73% 77% 58% 53.2% - -
WO3 Produced* mtu 5,884 4,737 32,408 18,768 38,292 23,505
WO3 Sold* mtu 6,039 4,077 32,015 19,515 38,054 23,592
Avg Realised price US$/mtu 456 1,189 591 965 478 1,004
Nominal cash cost** US$/mtu 701 1,452 147 349 232 571
*Note: 1 mtu (metric tonne unit) = 10kg 100% WO3
** Nominal cash cost being cost of goods sold plus inventory movement. Q2 FY2026 Mt Carbine nominal cash cost only included the all-
in operating cash cost to process the low-grade stockpile.
Both operations were heavily impacted by wet weather during the quarter resulting in an overall reduction in production
performance across the Group. Despite the wet weather negatively impacting production, the following key objectives
were achieved during the quarter:
• Reduced the Spanish debt by a further €1.5m and completed financial close of the €15m three-year prepayment
facility with Traxys in February 2026.
• Mt Carbine successfully completed the south wall cut back enabling the commencement of processing the higher-
grade Iolanthe Vein in the last week of March 2026. Ore benches will be progressively opened across April to enable
increasing higher-grade feed through Q4 2026.
• Approval received from Spanish Mines regulators for the installation and operation of additional contracted outsource
crushing unit to increase volume to the TOMRA Ore Sorters and enable full utilisation. This will enable increased
throughput as ore access in lower pit returns.
• Appointed Michael Nossal on 1 April 2026 as the new Independent Non-Executive Chairman
Following the progress in Q3 FY2026, the Company continues to improve its ramp up at Mt Carbine in April 2026 with
increasing average daily production relative to the prior three quarters and increasing higher grade ore availability.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 4
BARRUECOPARDO OPERATIONS
The Barruecopardo Tungsten Mine open pit as at the end of March 2026
Open Cut Mining
Northern area of Phase 6 at elevation 670 RL, including the access ramp and first blasts in the 660 RL bench.
Mining operations at Barruecopardo during Q3 FY2026 were heavily impacted by wet weather restricting pit access and
creating water‑management challenges. Material blasted totalled 2,556,468 tonnes, compared with 2,748,955 tonnes in
Q2 FY2026, while total material extracted decreased to 2,260,204 tonnes (Q2 FY2026: 2,505,085 tonnes).
Throughout the quarter, the operation remained actively focused on restoring access to the northern part of the bottom of
the pit as a priority, with mining and earthworks directed toward access development, pit floor preparation and water‑control
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 5
solutions. Continued advance through Phases 6 and 7 of the pit supported progressive improvements in pit geometry and
access conditions.
Ore mined totalled 162,086 tonnes, down from 468,220 tonnes in the prior quarter, reflecting restricted access to deeper,
higher‑grade ore zones during the access restoration phase. The ore accessed during the quarter was at a modest grade
consistent with the current mining horizon, with head grades expected to increase as access to lower elevations and
higher‑grade zones are re‑established.
Waste mined increased to 2,098,118 tonnes (Q2 FY2026: 2,036,865 tonnes), consistent with the deliberate prioritisation
of waste stripping, pit preparation and access works required to support dewatering activities and restore mining continuity.
Mining activities during the quarter were deliberately sequenced to maintain operational continuity while progressing pit
access restoration and preserving long‑term safety and flexibility.
By the end of the quarter, access restoration works and water‑management initiatives were advancing, with ore access
increasing through Phases 6 and 7 and the operation positioned to progressively regain access to the northern bottom of
the pit and higher‑grade ore zones in Q4 FY2026, subject to the performance of implemented control measures.
Processing
Processing operations at Barruecopardo during Q3 FY2026 were adversely impacted by reduced ore availability from the
pit and variability in feed conditions caused by the wet weather. Ore crushed totaled 413,303 tonnes, compared with
469,666 tonnes in Q2 FY2026, reflecting lower run‑of‑mine feed volumes during the quarter.
Sorter concentrate produced decreased to 26,002 tonnes (Q2 FY2026: 37,644 tonnes), consistent with the lower ore
delivery and reduced feed grades associated with the current mining horizon. Ore gravity processed totaled 218,297
tonnes, down from 236,603 tonnes in the prior quarter, with throughput constrained by feed availability rather than plant
capacity.
As a result of the wet weather, concentrate production for the quarter totaled 18,768 mtu of WO₃, compared with 32,408
mtu in Q2 FY2026.
Processing operations remained stable throughout the quarter, with the crushing, sorting and gravity circuits performing in
line with expectations given feed conditions. Mobile and supplementary processing options continued to be evaluated as
part of broader recovery planning; however, deployment timing remained sequenced behind pit access restoration and
subject to administrative and compliance requirements.
As access to the northern bottom of the pit improves and higher‑grade ore zones are progressively re‑established through
Phases 6 and 7, processing throughput and concentrate production are expected to improve in Q4 FY2026.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 6
MT CARBINE OPERATIONS
The Mt Carbine Tungsten Mine open pit as at the end of March 2026
Open Cut Mining
Mining operations advancing on the south wall early April, with next blasts in the 325-315 RL level
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 7
Mining activities at Mt Carbine during Q3 FY2026 were materially impacted by wet season conditions, which restricted pit
access and affected blast cadence creating variability in short-term mining productivity during the quarter. Material blasted
declined to 582,237 tonnes (Q2 FY2026: 906,604 tonnes), reflecting reduced blasting rates under persistent wet season
constraints.
With reduced blast rates, the availability of newly broken ground was limited, resulting in intermittent shortfalls in ore
delivery despite ongoing stripping and access works.
Notwithstanding these conditions, record quarterly material extraction of 821,678 tonnes was achieved during Q3 FY2026
(Q2 FY2026: 777,873 tonnes), supported by sustained waste movement and re‑handling of previously blasted material.
Ore mined increased materially to 95,795 tonnes, up from 56,583 tonnes in the prior quarter, reflecting improved ore
availability as access to the Iolanthe vein system was established. Waste mined remained broadly stable at 726,453 tonnes
(Q2 FY2026: 721,290 tonnes).
A revised mining sequence and April reforecast were developed to support consistent ore deliveries from higher‑grade
benches while avoiding future access constraints. Contractor support was engaged to supplement production drilling
capacity, and maintenance strategies were adjusted to improve fleet availability and drilling reliability going forward.
By the end of the quarter, mining momentum was rebuilding, with access continuing through the Iolanthe vein system and
progressing toward higher‑grade areas in Stage II, positioning the operation for improved ore delivery and more consistent
production performance in the subsequent period.
Processing
Processing operations at Mt Carbine during Q3 FY2026 were impacted by variable ore feed availability from the pit as
mining activities progressed through wet‑season constraints and access sequencing. Ore crushed during the quarter
totalled 103,345 tonnes, down from 157,965 tonnes in Q2 FY2026, reflecting both reduced run‑of‑mine supply and
temporary constraints within the crushing circuit rather than inherent plant capacity limitations.
Lower crushing throughput during the quarter was primarily attributable to the scheduled refurbishment of the main crusher
screen, which was undertaken in February to address wear and restore long‑term reliability. During this refurbishment
period, crushing operations were partially supported through the use of mobile crushing equipment to maintain continuity
of feed, albeit at reduced throughput relative to the fixed plant configuration. The refurbished screen was successfully
reinstated during March, restoring primary crushing capacity.
Ore Sorter concentrate produced decreased to 4,488 tonnes (Q2 FY2026: 6,707 tonnes), consistent with lower crushing
throughput during the quarter. Gravity circuit processed 45,238.5 tonnes, compared with 64,278 tonnes in the prior quarter,
with plant utilisation constrained by upstream feed continuity.
Despite lower throughput, processing efficiency improved during Q3 FY2026, supported by higher‑quality ore feed as
access to the Iolanthe vein system progressed. Average gravity plant feed grade increased to 0.140% WO₃, up from
0.126% WO₃ in Q2 FY2026, while recovery improved to 76.7% (Q2 FY2026: 72.8%). These improvements partially offset
lower feed volumes.
WO₃ production for the quarter totalled 4,737 mtu, compared with 5,884 mtu in Q2 FY2026, with the reduction primarily
attributable to lower throughput during the period. To mitigate the impact of the crusher screen outage and accelerate
recovery of crushing volumes, a specialist crushing contractor has been engaged to provide additional crushing capacity
and lift overall throughput through the rest of the year. As mining access continues to improve and ore delivery increases,
processing performance is expected to benefit from both higher feed rates and improved head grades, supporting stronger
production outcomes in subsequent periods.
FINANCIAL MANAGEMENT AND CONTROL
Funding
During the quarter, the Company reduced its Spanish debt by a further €1.5m and completed transaction documentation
for a three‑year €15 million prepayment financing facility with Traxys Europe S.A. The facility is repayable via set‑off against
monthly tungsten concentrate deliveries and carries an interest rate of one‑month EURIBOR plus 5.5%, with no principal
repayments required in the first six months of financial close.
In conjunction with the financing facility, the Company entered into a five‑year marketing and distribution agreement with
Traxys Europe S.A. covering 3,500 tonnes of WO₃ production from the Barruecopardo Mine, providing long‑term sales
alignment with the financing structure.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 8
ASX Announcement 24th
February 2026: EQR Reduces Spanish Debt and Refinances Remaining €15M.
Quarterly Cash Flow Summary
At 31 March 2026, the Company had A$15.8m cash on hand and A$15m in accounts receivable positioning it well as Mt
Carbine ramps up its production and both operations recover from an extensive wet season.
During the quarter, the Company generated A$32.6m in revenue resulting in A$19.8m in cash receipts after historical
prepayments were reduced by A$6.9m and a A$5.9m increase in accounts receivable.
Cash Flows from Operating Activities
In Q3 FY2026, net cash outflows from operating activities for the Group amounted to A$11.5 million due to reduced
production because of wet weather, timing of shipments generating an increase in accounts receivables and a substantial
reduction in historical prepayments.
Cash Flows from Investing Activities
In Q3 FY2026, net cash used in investing activities totalled A$4.4 million to support the ongoing ramp up and production
efficiencies at both operations.
Cash Flows from Financing Activities
In Q3 FY2026, net cash from financing activities totalled A$10 million. This primarily consisted of A$19m of options
exercised, A$31m of borrowing repaid and an opening of the new Traxys prepayment facility of A$25m offset by A$3m in
equipment finance lease payments.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 9
CORPORATE
The Company continued to build its corporate capability and capacity during the quarter with the appointment of Virna
Trout as General Counsel along with a new Group IT Manager and Group Reporting Manager.
To support the increased capability and capacity of the Group’ Corporate team, a 5-year office lease in the Brisbane CBD
commencing 1 June 2026 was entered.
TUNGSTEN MARKETS
Tungsten markets strengthened significantly during Q3 FY2026, supported by structural supply tightness, and ongoing
Chinese export controls, which materially constrained availability across global supply chains. Fastmarkets reported that
seaborne APT and tungsten concentrate markets experienced extreme volatility, with prices rising sharply as downstream
consumers sought to secure supply amid geopolitical uncertainty and increased strategic stockpiling. While short-term
price corrections were observed late in the quarter, market commentary continues to point to persistent tightness and
elevated pricing, driven by limited new supply and sustained demand from industrial and defence sectors.
12 Month History of APT Low-Price. Price on 31st
March 2026. Source: Fastmarkets. Tungsten APT 88.5% WO3
(min), CIF Rotterdam and Baltimore, duty-free, $/mtu WO3
SUSTAINABILITY & SOCIAL PROGRAMS
For more information on the Company’s ESG commitments and ongoing initiatives, please visit EQR’s LinkedIn, Saloro’s
LinkedIn and the Sustainability page on EQR’s Website.
EXPLORATION ACTIVITIES / RESERVES AND RESOURCES
Mt Carbine Exploration
A drilling contractor is currently undertaking exploration drilling on the northern part of the Mt Carbine project area (EPM
14871 & 14872) to advance exploration targets and support longer‑term resource. In addition, Grade control drilling is
being undertaken in parallel with production drilling to refine near‑term grade definition and support estimates of metal
units to be produced in H2 FY2027.
300
800
1,300
1,800
2,300
2,800
3,300
($US/mtu)
12 months - APT Low Price (CIF EU/US) $US
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 10
Wolfram Camp
Exploration activities at Wolfram Camp during the quarter were focused on planning and program preparation, with no
material on-ground drilling undertaken. High-level target delineation and prioritisation have been completed, providing the
basis for upcoming exploration activities.
Detailed exploration program design is ongoing, with initial field activities scheduled to commence in June 2026. A drill
program targeting the existing resource and near-mine resource expansion areas is currently being designed, with drilling
expected to commence following completion of the Mt Carbine drilling program, anticipated around July 2026, subject to
operational sequencing.
The Company is engaging with specialist technical contractors to support exploration program design and execution,
including drilling and geophysical service providers. In parallel, work has commenced on the Native Title process, with
specialist consultants engaged to support regulatory and stakeholder engagement requirements.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 11
In addition, detailed design of a geophysical Induced Polarisation (IP) survey program is being progressed to refine targets
ahead of drilling.
Mineral Resource and Ore Reserves
There has been no material change to the Company's Mineral Resources and Ore Reserves since the last publication. For
the latest information, please refer to:
• Mt Carbine & Barruecopardo (Life Of Mine & production target clarification): ASX Announcement 12 December 2025:
“Clarification of Production Targets and Life of Mine Plans”.
• Mt Carbine Mine: EQR Annual Report FY2025
• Barruecopardo Mine: ASX Announcement 22 October 2025: “EQ Resources Barruecopardo Mine Increases Ore
Reserves by 39%”.
Tenements
There have been changes to the tenement holdings of the Company and its controlled entities. The current tenement
interests are disclosed below in accordance with ASX Listing Rule 5.3.3.
Australia
Note: EPM 14871 & EPM 14872 Renewal lodged, pending registration.
Location Holding Entity
Beneficial
Interest
Interest
Acquired or
Disposed
Area Expiry date
Queensland, Australia
ML 4867 Mt Carbine Quarries Pty Ltd 100% N/A 358.5 ha 31/07/2041
ML 4919 Mt Carbine Quarries Pty Ltd 100% N/A 7.891 ha 31/08/2041
EPM 14871 EQ Resources Limited 100% N/A 10 sub-blocks 12/12/2025
EPM 14872 EQ Resources Limited 100% N/A 21 sub-blocks 11/12/2025
EPM 28898 EQ Resources Limited 100% 17/06/2024 147 sub-blocks 17/06/2029
ML = Mining Lease; EPM = Exploration Permit for Mineral (Qld); EL = Exploration License (NSW)
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 12
Spain
Location Holding Entity
Beneficial
Interest
Interest
Acquired
Area Expiry date Granting
Salamanca, Spain
C.E. Barruecopardo, 6.432-10 Saloro, SLU 100% 18/01/2024 2,100 Ha 1/11/2041 20/11/2014
P.I. Saldeana 1a
Fracción, 6.432-11 Saloro, SLU 100% 18/01/2024 13 Aug.* 13/08/2001
P.I. Saldeana 2a
Fracción, 6.432-12 Saloro, SLU 100% 18/01/2024 13 Aug.* 13/08/2001
P.I. Milano, 6.432-20 Saloro, SLU 100% 18/01/2024 29,000 Ha 13 Aug.* 13/08/2011
P.I. Cortegana, 6.570 Saloro, SLU 100% 18/01/2024 16,700 Ha 14 Nov.* 14/11/2006
P.I. Almonaster, 6.572 Saloro, SLU 100% 18/01/2024 4,300 Ha 14 Nov.* 14/11/2006
P.I. Aracena, 6.649 Saloro, SLU 100% 18/01/2024 5,300 Ha 30 Oct.* 30/10/2008
P.I. Brincones, 6.834 Saloro, SLU 100% 18/01/2024 6,100 Ha 7 May* 7/05/2013
C.E. = Mining Lease; *P.I. = Exploration Permit w hich is renew ed annually.
29,300 Ha
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 March 2026 Page 13
Released on the authority of the Board by: Further Enquiries:
Craig Bradshaw Peter Taylor
Managing Director Investor Relations
M: 0412 036 231
E: peter@nwrcommunications.com.au
About EQ Resources Limited
EQ Resources Limited is a leading global tungsten mining company dedicated to sustainable mining and processing
practices. The Company is listed on the Australian Securities Exchange, with a focus on expanding its world-class tungsten
assets at Mt Carbine in North Queensland (Australia) and at Barruecopardo in the Salamanca Province (Spain). The
Company leverages advanced minerals processing technology and unexploited resources across multiple jurisdictions,
with the aim of being a globally leading supplier of the critical mineral, tungsten. The Company aims to create shareholder
value through the exploration and development of its current project portfolio whilst continuing to evaluate corporate and
exploration opportunities within the new economy and critical minerals sector globally.
Forward-looking Statements
This announcement may contain forward-looking statements. Forward-looking statements address future events and
conditions and, therefore, involve inherent risks and uncertainties. Actual results may differ materially from those currently
anticipated in such statements. Particular risks applicable to this announcement include risks associated with planned
production, including the ability of the Company to achieve its targeted production outline due to regulatory, technical or
economic factors. In addition, there are risks associated with estimates of resources, and there is no guarantee that a
resource will have demonstrated economic viability as necessary to be classified as a reserve. There is no guarantee that
additional exploration work will result in significant increases in resource estimates. Neither the Australian Securities
Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Australian Securities Exchange)
accepts responsibility for the adequacy or accuracy of this announcement.
Follow us:
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
EQ RESOURCES LIMITED
ABN Quarter ended (“current quarter”)
77 115 009 106 31 March 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(9 months)
$A’000
1. Cash flows from operating activities
19,792 56,280
1.1 Receipts from customers
1.2 Payments for
(2) (2)
(a) exploration & evaluation
(b) development (0) (6)
(c) production (21,181) (53,123)
(d) staff costs (8,747) (24,747)
(e) administration and corporate costs (1,232) (3,679)
1.3 Dividends received (see note 3) - -
1.4 Interest received 104 187
1.5 Interest and other costs of finance paid (566) (3,799)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other
- Diesel Fuel Tax Credits
- Grants
- Traineeship Subsidies
- Other
354
-
-
-
904
-
4
-
1.9 Net cash from / (used in) operating
activities
(11,478) (27,981)
2. Cash flows from investing activities
- (1,359)
2.1 Payments to acquire or for:
(a) entities
(b) tenements (315) (312)
(c) property, plant and equipment (2,627) (6,588)
(d) exploration & evaluation (if capitalised) - (24)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(9 months)
$A’000
(e) investments - -
(f) other non-current assets - -
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - 6
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) (1,428) (1,428)
2.6 Net cash from / (used in) investing
activities
(4,369) (9,959)
3. Cash flows from financing activities
- 55,748
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- 683
3.3 Proceeds from exercise of options 19,177 19,177
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(167) (4,240)
3.5 Proceeds from Borrowings - -
3.6 Repayment of borrowings (30,930) (50,776)
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other
- Lease Repayments
- Offtake prepayment facility
(2,897)
24,799
(4,534)
36,164
3.10 Net cash from / (used in) financing
activities
9,980 52,221
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
21,977 1,873
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(11,478) (27,981)
Appendix 5B
Mining
Share your feedback