Investor Update / Webinar
Released
Released
Announcement PDF
EQ RESOURCES LIMITED
Investor Update / Webinar
09 October 2024
ASX : EQR
Disclaimer
Competent Person's Statement
• The information in this presentation partly relates to the outcomes of the Mt Carbine Bankable Feasibility Study Update (May 2023) and most recent drilling announcements, made available
through the Company’s website www.eqresources.com.au/.
• The Company confirms that it is not aware of any new information that materially affects the information included in the corresponding market announcements and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcements continue to apply and have not materially changed. The Company confirms that the
form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements.
General Disclaimer
• The material contained in this document is a presentation of general information about the Company's activities current as at the date of this presentation. It is provided in summary and does
not purport to be complete. You should not rely upon it as advice for investment purposes, as it does not take into account your investment objectives, financial position or needs. These
factors should be considered, with or without professional advice, when deciding if an investment is appropriate.
• This document may contain forward-looking statements with respect to the financial condition, results of operations, and business strategy of the Company. These forward-looking statements
are based on estimates, projections and assumptions made by the Company about circumstances and events that have not yet taken place. Although the Company believes the forwardlooking statements to be reasonable, they are not certain. Forward-looking statements involve known and unknown risks, uncertainties and other factors that are in some cases beyond the
Company's control, and which may cause actual results, performance or achievements to differ materially from those expressed or implied by the forward-looking statements (and from past
results).
• The Company makes no representation or warranty as to the accuracy of any forward-looking statements in this document and undue reliance should not be placed upon such statements.
• Forward-looking statements may be identified by words such as “aim”, “anticipate”, “assume”, “continue”, “could”, “estimate”, “expect”, “intend”, “may”, “plan”, “predict”, “should”, “will”, or
“would” or the negative of such terms or other similar expressions that are predictions of or otherwise indicate future events or trends. The forward-looking statements included in this
document speak only as of the date of this document. The Company does not intend to update the forward-looking statements in this document in the future.
2
Talking Points
Corporate Update
Mt Carbine
Saloro
Tungsten Market Dynamics
1.
2.
3.
Wolfram Camp
3
Corporate Update
EQR Group Monthly Average mtu : September Production Record 20,721 mtu*
Share Price
A$0.056 per share
Securities on Issue
Shares 2.24B / Options 205m
Market Capitalisation
A$ 125.3 million
Top 20 Shareholders
>60% (9% Board/Management)
0.070
370
0.060
360
0.050
350
0.040
340
0.030
330
0.020
320
0.010
310
0.000
300
EQR Share Price
APT Price USD
Share Price AUD
Key Statistics
APT Price
* Source: FastMarkets APT Price Rotterdam (US$/mtu, mtu = 10kg WO3)
Production Output EQR Group (monthly average, in mtu)
*1mtu = 10kg WO3
See ASX Announcement: “Quarterly Tungsten Production at EQ Resources up 31%” Dated 02 October 2024
4
Mt Carbine Production
Ore Grade and Operational Improvements
Mt Carbine 2024 Monthly WO3 Production Ramp Up
Crushing Plant / Ore Sorter Plant Throughput
12,000
100,000
11,000
90,000
10,000
80,000
9,000
70,000
8,000
60,000
Tonnes
mtus
7,000
6,000
50,000
5,000
40,000
4,000
30,000
3,000
20,000
2,000
10,000
1,000
-
Jan-24
Feb-24
Mar-24
Apr-24
May-24
Jun-24
Jul-24
Aug-24
Sep-24
May-24
Jun-24
Crushing Plant Throughput
Jul-24
Aug-24
Ore Sorter Plant Throughput
Sep-24
5
Mt Carbine Updates
Owner-Operator Model , Operations Update
Mining Fleet
✓ Cat 90T Excavator x1 - On site & Commissioned
✓ 50T excavator x1 - On site & Commissioned
✓ Dump truck Volvo A60H 60 tonnes - On site & Commissioned
✓ Dump truck Bell B50 x2 - On site & Commissioned
✓ Dozer x2 – On site & Commissioned
>0.2% WO3
✓ Water Cart - On site & Commissioned
✓ Grader - On site & Commissioned
Operations
✓ Day + Night shifts transition successful
✓ 12hrs operation successfully implemented
✓ 90t excavator → currently ramping up 10-12k tonnes / day
✓ Reporting + Accounts + Safety + HR department absorbed extra operations
smoothly
✓ Technical service team keeping up existing system + implementing new
procedures
✓ Maintenance team setting up maintenance schedule ongoing
6
Mt Carbine Updates
Ore Grade and Operational Improvements
7
Mt Carbine Updates
Ore Grade and Operational Improvements
8
Saloro Updates
Grade Control, Processing and Recovery Improvements
Saloro 2024 Monthly WO3 Production Ramp Up
11000
10000
mtu
9000
8000
7000
6000
5000
>0.2% WO3
4000
Jan-24
Feb-24 Mar-24 Apr-24 May-24 Jun-24
See ASX Announcement: “2024 Annual Report” Dated 30 September 2024
Jul-24
Aug-24 Sep-24
9
Tungsten Market Dynamics
EQR production increase coincides with China tightening export control measures, US 25% tariff on Chinese tungsten products
Current Production Run-Rate Reaches 17% of US Monthly Tungsten Imports,
Narrowing Gap with China's 27% Share
Good Timing For EQR Yearly Production To Be Ramping Up
EQR Yearly Production Forecast
600,000
500,000
mtus
400,000
300,000
200,000
100,000
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Saloro
Mt Carbine
See ASX Announcement: “Quarterly Tungsten Production at EQ Resources up 31%” Dated 02 October 2024
See Article: “80% of the world’s tungsten supply chain is owned by China
but this may not last for much longer”
10
Wolfram Camp Updates
EQR Identifies 5 Exploration Targets for Wolfram Camp
Highlights:
• Potential for Restart:
Work program for 5 high-potential targets supports the
redevelopment of Wolfram Camp.
• Historical Resource:
2.95Mt @ 0.279% WO₃ remaining under EQR management.
>0.2% WO3
• Supports Queensland’s Critical Minerals
Strategy:
Redevelopment aligns with EQR's growth strategy and
Queensland’s Critical Minerals Strategy and Resources
Industry Development Plan.
• Low-Grade Stockpile:
~5 million tonnes of tungsten, molybdenum, and bismuth
stockpiles available for immediate evaluation.
See ASX Announcement: “EQR Identifies 5 Exploration Targets for Wolfram
Camp” Dated 07 October 2024
11
Site Contact:
Investor Relations:
Kevin MacNeill
Chief Executive Officer
T: +61 438 542 260
E: kmacneill@eqresources.com.au
Peter Taylor
NWR Communications
T: +61 412 036 231
E: peter@nwrcommunications.com.au
Registered Office:
Mt Carbine Office:
Level 4, 100 Albert Road
South Melbourne, VIC 3205
Australia
E: info@eqresources.com.au
6888 Mulligan Highway,
Mt Carbine Qld 4871
PO Box 1496, Mareeba Qld 4880
www.eqresources.com.au