Mt Carbine Hits Quarterly Production Record
Released
Released
Announcement PDF
resourcing the new economy for a better tomorrow
11 April 2024
MT CARBINE HITS QUARTERLY PRODUCTION RECORD,
WITH XRT SORTER EXPANSION WELL UNDERWAY
EQ Resources Ltd is a global tungsten producer with mining activities in Australia and Spain.
Highlights:
-
Record tungsten concentrate production (50% WO3 equivalent) at the Mt Carbine mine despite
recovering from Cyclone Jasper
-
Expanded mining rates, crushing throughput and record XRT Ore Sorter production supported
a quarter-on-quarter improvement of +38% in tungsten output (Q2FY2024 vs. Q3FY2024)
-
Additional new generation XRT Ore Sorter ordered, in combination with a technology upgrade
of the existing units boosting the Mt Carbine sorting capacity by >100%
EQ Resources Limited (“EQR” or “the Company”) is pleased to announce that it has ended the third quarter of
the 2024 Financial Year with record tungsten concentrate production (50% WO3 equivalent) from its Mt Carbine
operations. The Mt Carbine operation produced 507 tonnes in the quarter despite recovering from Tropical
Cyclone Jasper and the Far North Queensland wet season. This represents a quarter-on-quarter improvement
at Mt Carbine of +38% in tungsten output (Q2FY2024 vs. Q3FY2024). The EQR Group produced 973 tonnes,
as seen in Fig. 2, when including the Barrucopardo concentrate production.
Record concentrate production was achieved at Mt Carbine thanks to the further ramp-up of the operations in
the Open Pit. Nearly 800,000 tonnes of material were extracted in Q3FY2024, and the Crushing Plant
production increased to 80,000 tonnes per month for February and March. The Company ended the quarter
with a stockpile of 30,000 tonnes of crushed material waiting to be processed through the TOMRA XRT Ore
Sorters (“XRT Sorters”). The XRT Sorting Plant also had a record quarter, processing 132,000 tonnes of feed
material and producing a continuous stream of sorter concentrate for downstream processing in the Gravity
Plant.
Material extracted from Open Pit (kt)
1,000
795
800
600
400
497
273
200
0
Q1 FY2024
Q2 FY2024
Q3 FY2024
Fig.1 - Quarterly Comparison of Material Extraction from Mt Carbine Open Pit
REGISTERED OFFICE: Level 4, 100 Albert Road, South Melbourne, VIC 3205
PRINCIPAL PLACE OF BUSINESS: 6888 Mulligan Highway, Mt Carbine Qld 4871
POSTAL ADDRESS: PO Box 1496, Mareeba Qld 4880
ABN: 77 115 009 106 (ASX: EQR)
T: (07) 4094 3072 | F: (07) 4094 3036 | W: eqresources.com.au
resourcing the new economy for a better tomorrow
EQR Group Concentrate Production 50% Equivalent (t)
1000
900
800
700
600
500
400
300
200
100
0
466 **
423
136
151
45
50
Q3 FY2023
Mt Carbine
141
Q4 FY2023
Q1 FY2024
Saloro
Monthly Average (t)
368
123
507*
317
Q2 FY2024
Q3 FY2024
Linear (Monthly Average (t))
Fig.2 – Quarterly Comparison of WO3 Concentrate Production (Mt Carbine* in wet tonnes and Barruecopardo**
in dry tonnes) - Saloro acquisition and concentrate represented from Q3FY2024
Additional new generation XRT Ore Sorter ordered & existing units being upgraded
On the back of increasing mining and crushing rates, the Company ordered a fourth new generation TOMRA
XRT Ore Sorter and will upgrade the existing two XRT Sorters currently working with the latest ejection
modules and updated software. The historical XRT Sorter #1 will serve as a backup unit.
The additional unit and respective upgrades will boost sorting capacity by more than 100% to treating fresh
ore from the Andy White Open Pit and Low-Grade Stockpile material at Mt Carbine, in line with the recently
announced plan of the Company to double overall processing capacity by the end of 2024 (see ASX
announcement “Mt Carbine Receives Additional Equipment For Doubling Of Throughput Capacity” dated 20
March 2024). The new generation XRT Sorter is expected to be delivered before the end of Q4FY2024, while
the refurbished XRT Sorters should be operational soon after.
Fig.3 - Current XRT Sorter unit at Mt Carbine (two in operation, one under refurbishment)
Page 2
resourcing the new economy for a better tomorrow
Upon delivery of the new unit, EQR will own six high-tech XRT Sorters, including the two new generation XRT
Sorters at the Company’s recently acquired Saloro tungsten mine in Barruecopardo, Spain. Saloro’s
XRT Sorters at the Barruecopardo mine continue to treat and upgrade fresh- and stockpiled ore, providing
additional feed to the existing downstream processing plant. Results during commissioning and ramp-up of
these units exceeded the Company’s expectations (see ASX announcement “Saloro’s XRT Sorting
Performance Exceeds Expectations, Adding 26% More Material To Gravity Plant” dated 15 February 2024).
Fig.4 - Saloro’s XRT Sorting Plant fully commissioned; 2x Tomra XRT Sorters
(COM Tertiary XRT 1200)
EQR’s Chief Executive Officer, Kevin MacNeill, commented: "The additional new generation XRT Ore Sorter
and upgrade to the ejection modules of our existing units reduces air- and power consumption, while expanding
sorting capacity at Mt Carbine by up to 100% and increasing the sorter concentrate grade produced.”
“The benefits resulting from the continuous improvements of sensor-based sorting technologies to the bottom
line at both Mt Carbine and Saloro are a game changer, and we are pleased having a strong technical team
behind both our sorting operations. Introducing the new generation XRT Sorters and software upgrades will
allow EQR to maintain its position as the Western world’s leading independent producer of tungsten
concentrates.”
“The timing is exceptionally good, as the global price of tungsten concentrate is firming. Traders in the key
end-user markets report tight supply of tungsten concentrate, pushing prices modestly higher. EQR’s ambition
is to build on its market-leading position as we ramp up to full production at both Mt Carbine and
Barruecopardo.”
Released on authority of the Board by:
Kevin MacNeill
Chief Executive Officer
Further Enquiries:
Peter Taylor
Investor Relations
0412 036 231
peter@nwrcommunications.com.au
About the Company
EQ Resources Limited is a leading tungsten mining company dedicated to sustainable mining and processing practices.
The Company is listed on the Australian Securities Exchange, with a focus on expanding its world-class tungsten assets
at Mt Carbine in North Queensland (Australia) and at Barruecopardo in the Salamanca Province (Spain). The Company
leverages advanced minerals processing technology and unexploited resources across multiple jurisdictions, with the aim
of being a globally leading supplier of the critical mineral, tungsten. While the Company also holds gold exploration licences
in New South Wales (Australia), it aims to create shareholder value through the exploration and development of its current
project portfolio whilst continuing to evaluate corporate and exploration opportunities within the new economy and critical
minerals sector globally.
Page 3
resourcing the new economy for a better tomorrow
Forward-looking Statements
This announcement may contain forward-looking statements. Forward-looking statements address future events and
conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently
anticipated in such statements. Particular risks applicable to this announcement include risks associated with planned
production, including the ability of the Company to achieve its targeted production outline due to regulatory, technical or
economic factors. In addition, there are risks associated with estimates of resources, and there is no guarantee that a
resource will have demonstrated economic viability as necessary to be classified as a reserve. There is no guarantee that
additional exploration work will result in significant increases to resource estimates. Neither the Australian Securities
Exchange nor its Regulation Services Provider (as that term is defined in policies of the Australian Securities Exchange)