Quarterly Activities Report - Quarter ended 31 December 2025 Page 1
EQ Resources Limited
Quarterly Activities Report
Quarter Ended 31 December 2025
HIGHLIGHTS
TUNGSTEN MARKET
Fastmarkets Ammonium Paratungstate (“APT”) CIF Rotterdam/Baltimore low-price was US$900 per
mtu* on 2 January 2026, almost +50% increase Quarter-On-Quarter (QoQ) and a +181% increase
Year-On-Year from US$320 on 3 January 2025. The average low-price for the quarter was US$698
per mtu.
Chinese APT prices remained higher than the European APT prices demonstrating that the structural
supply deficit continues globally with record tungsten imports into China continuing.
BARRUECOPARDO OPERATIONS
Record mining and processing performance at Barruecopardo, with record material blasted (2.75 Mt),
record material extracted (2.51 Mt), record material crushed (469,666 tonnes) and record material
sorted (177,242 tonnes) during Q2 FY2026.
Second-highest quarterly concentrate production on record of 32,408 mtu, supported by improved
plant availability and ore sorting performance, including record monthly production exceeding 12,000
mtu in October 2025, with consistent shipments delivered to key customers throughout the quarter.
MT CARBINE OPERATIONS
Record mining activity at Mt Carbine, with 906,604 tonnes blasted in Q2 FY2026, exceeding the
previous quarterly record of 603,309 tonnes, and 777,873 tonnes extracted, as accelerated South Wall
stripping and ramp development advanced access to the Iolanthe ore body in the Stage II pit.
Remains on track to access the higher-grade Iolanthe vein in Q3 FY2026.
FUNDING**
Strengthened balance sheet and liquidity through A$34 million equity raising, alongside the agreed
conversion of the remaining A$7.25 million of Oaktree pre-royalty debt to equity*** enabled the
Company to reset its balance sheet.
Current liabilities were reduced by A$24.45 million including a €3.5m reduction in Spanish debt,
complementing the binding term sheet entered with Traxys to refinance €15 million of existing debt
facilities.
CASH GENERATION
Cash flow from operations for the Group was positive, generating A$1.15 million for the quarter with
the Barruecopardo operation generating A$14.2 million.
Cash receipts from sales increased 49% to A$21.8 million for the quarter.
Cash on hand at 31 December 2025 of A$22 million with a further A$3.2 million available via existing
debt facilities.
Notes: * 1 mtu (metric tonne unit) = 10 kg 100% WO3, **All financial numbers are quoted in Australian dollars unless otherwise stated.***
Subject to Shareholder approval.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 2
EQR GROUP Q2 FY2026 - PRODUCTION SUMMARY
Operations Mt Carbine Saloro EQR Group
Unit
Q1
FY2026
Q2 FY2026 Q1 FY2026 Q2 FY2026
Q1
FY2026
Q2
FY2026
Material Blasted t 175,272 906,604 1,265,302 2,748,955 1,440,575 3,655,560
Total Tonnes Mined t 110,768 777,873 1,289,413 2,505,085 1,400,181 3,282,958
Waste Mined t 110,768 721,290 1,042,410 2,036,865 1,153,178 2,758,155
Ore Mined t - 56,583 247,003 468,220 247,003 524,803
Strip Ratio W:O - 12.7 : 1 4.2 : 1 4.4 : 1 4.7 : 1 5.3 : 1
Closing Ore Stock - ROM t 888 70,236 456,330 250,715 457,218 587,382
Closing Ore Stock - LGS t 9,483,819 9,393,566 N/A N/A 9,483,819 9,393,566
Crushing Plant Feed t 115,509 157,965 333,484 469,666 448,993 627,631
Gravity Plant Feed t 46,905 64,278 247,628 236,603 294,533 300,881
Gravity Plant Grade % 0.133% 0.126% 0.175% 0.236% - -
Recovery % 74% 73% 56% 58% - -
WO3 Produced* mtu 4,610 5,884 24,225 32,408 28,834 38,292
WO3 Sold* mtu 4,074 6,039 20,324 32,015 24,681 38,054
Avg Realised price US$/mtu 343 456 381 591 374 478
Nominal Cash Cost** US$/mtu 723 701 210 147 292 232
*Note: 1 mtu (metric tonne unit) = 10 kg 100% WO3
** Barruecopardo nominal cash cost adjusted for prepayments and historical overdue payments made to contractors. Mt Carbine nominal
cash cost only includes the all-in operating cash cost to process the low-grade stockpile.
During the quarter the Company delivered on the following key objectives to set the platform for a successful 2026:
Successfully raised A$34 million in capital to reset the balance sheet and ensure sufficient financial resources to
minimise any risk to deliver on the South Wall cutback at Mt Carbine, accessing the high grade 1.6mt of 0.262% WO3
Iolanthe Vein.
Refinanced the Spanish Debt due in December 2025 and January 2026, entering a binding term sheet with Traxys on
8 December to refinance €15m of the Spanish debt (with the remaining €5 million being paid out in cash generated by
Barruecopardo operations).
Continuing to focus on the optimisation of the Barruecopardo operation in Spain leveraging the installation and
commissioning of processing plant modifications (including a third ore sorter) to maximise recovery and throughput.
Produced a record 12,006 mtu at Barruecopardo mine in October 2025, complemented by record mining and
processing activity throughout the quarter which resulted in the generation of A$14 million in free operating cashflows.
Mt Carbine’s record mining activity has accelerated the progress on the South Wall cutback with 650,000 tonnes
remaining to enable full access to the Iolanthe Vein – of which, only 250,000 tonnes is required to be excavated to
have partial access.
Engaged an executive search firm for the recruitment of an independent non-executive chairman which is expected to
be appointed in Q3 FY2026.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 3
HEALTH, SAFETY & ENVIRONMENT
Above: 12-Month Lost Time Injury Rolling Frequency Rate Graph per Million Working Hours
Barruecopardo Operations
In Q2 FY2026, Barruecopardo maintained a strong focus on safety performance and workforce engagement, with accident
and incident frequency rates remaining below Spanish mining sector benchmarks.
Positive safety indicators remained robust across the operation. Participation in the “Step Back, Take 5” program continued,
with 1,270 risk assessments completed during the quarter. Safety assurance activities included 134 internal safety
sessions, ongoing alcohol and drug testing (3,811 tests conducted), and continued monitoring of respirable crystalline
silica exposure. Training remained a key focus, with 6 new employee inductions, 29 training sessions, and regular toolbox
talks delivered across operational areas.
Environmental management continued to be fully integrated into daily operations. Habitat restoration and planting
programs progressed, with more than 600 plants, covering an area of 10 hectares, established under regional
environmental initiatives. Barruecopardo also continued its involvement in rehabilitation projects and bird-tracking
programs, including the monitoring of endangered species nesting within the pit area, being part of the EU-funded
OPTIMINER R&D&I project, whose objective is to optimise the mining of critical raw materials through advanced and
sustainable technologies.
As part of the Company’s community engagement efforts, the Company highlights the visit of the Guardia Civil’s Public
Security Unit, and, as part of the annual celebrations for the patron saint of mining in Spain, the planting of a tree by the
children from the Barruecopardo school in the mine’s Tree Park.
Left: Local students from the Barruecopardo school planting a tree on site; Right: Visit from the Civil Guard USECIC
49 49
54 54
49
40
37
29
33
41
36
49 48
11
13
19
16
19
22 22 23 23 23
26
23 23
-
10
20
30
40
50
60
Mt Carbine Barruecopardo LTIFR Mining (Spain)
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 4
Mt Carbine Operations
In Q2 FY2026, safety performance remained a strong operational focus, supported by continued reinforcement of site
procedures, workforce training and compliance initiatives.
Positive safety indicators continued to demonstrate active workforce engagement. During the quarter, the Company
conducted 5,439 alcohol tests and 3 post-incident drug tests, in line with site safety management plans. A total of 5,875
“Take 5” safety observations were completed across operations, and 7 toolbox talks were delivered covering operational,
equipment and environmental risks. Targeted training activities were also undertaken, including verification of
competencies for mobile equipment operation, site-specific inductions and refresher training for operational personnel.
Environmental management and water stewardship remained a key focus throughout the quarter, particularly in
preparation for the transition to wet crushing and screening operations. Dam water-level monitoring, pit dewatering, pipeline
installation and water recycling infrastructure works progressed to support higher processing rates while maintaining
compliance with environmental approvals and site operating conditions.
BARRUECOPARDO OPERATIONS
Above: The Barruecopardo Tungsten Mine open pit as at the end of December 2025
During Q2 FY2026, Barruecopardo delivered a strong operational quarter, underpinned by higher mining rates, improved
feed continuity and ongoing optimisation across the crushing, sorting and gravity circuits. The quarter included several new
production records, reflecting improved execution across drilling and blasting, material movement and plant availability.
Open Cut Mining
Mining activity focused on maintaining consistent ore exposure and progressing pit development, supported by enhanced
drilling and blasting delivery and continued emphasis on grade control in narrow, high-grade domains.
Material movement performance was strong, with record material blasted of 2,748,955 tonnes (up from 2,299,959 tonnes
in Q1 FY2024) and record material extracted of 2,505,085 tonnes (up from 2,201,321 tonnes in Q1 FY2024), comprising
2,036,865 tonnes of waste and 468,220 tonnes of ore.
In addition to achieving record performances and production targets, operations prioritised deepening the southern area
of the pit to establish a water storage zone, supporting continued production in the central pit area through the rainy season.
Waste works continued in Phase 6, while the Phase 7 pushback was temporarily paused to reduce delays at the bottom
of the pit and maintain operational continuity.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 5
Pictured: Northern area of Phase 6 at elevation 680 RL, including the access ramp and the 670 RL bench.
Processing
Processing performance strengthened across the quarter, supported by improved crushing reliability, higher ore sorter
utilisation and incremental circuit upgrades.
Barruecopardo delivered record crushing and sorting performance, with material crushed totalling 469,666 tonnes (up from
418,124 tonnes in Q2 FY2025) and material sorted totalling 177,242 tonnes (up from 135,210 tonnes in Q4 FY2025),
supported by improved upstream continuity and stronger sorter contribution to feed upgrading.
Plant recovery remained broadly consistent (just below 60% range), with variability driven primarily by head grade and ore
characteristics. Targeted maintenance and technical adjustments were completed across crushers, belts, screens, jigs and
hydraulics to improve availability and recovery stability. Following the installation of the 3rd
ore sorter, ongoing reliability
work continued on the first two sorters, with escalation and troubleshooting undertaken in collaboration with TOMRA
technicians to resolve persistent electrical issues.
Gravity circuit performance continued to improve following repairs and optimisation efforts. Additional scavenging capacity
was advanced and is expected to reduce tail grades and improve overall recovery once fully commissioned. Seven
Holman-Wilfley tables have been purchased to improve reliability in the tabling circuit, with commissioning targeted by the
end of Q3 FY2026.
Concentrate production was strong, delivering the second-best quarterly result of 32,408 mtu, compared with the record
of 33,249 mtu achieved in Q2 FY2025. Saloro also achieved its highest monthly concentrate production on record,
exceeding 12,000 mtu following the recommissioning of the multi-deck screen. This improved size control after the
resolution of permitting issues; ASX Announcement 4 November 2025: 'Barruecopardo Mine Sets Record production in
Oct 2025’. Shipments continued throughout the quarter to key customers, supported by consistent container scheduling.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 6
MT CARBINE OPERATIONS
Above: The Mt Carbine Tungsten Mine open pit as at the end of December 2025
Operational activities at Mt Carbine during Q2 FY2026 marked a clear transition from stabilisation to execution, with a
significant increase in mining activity following the reset program initiated in the prior quarter. Improved funding enabled
fully funded stripping operations, higher equipment availability and a sustained ramp-up in material movement, while
maintaining a strong focus on safety, compliance and site integrity.
Open Cut Mining
Mining operations accelerated materially during the quarter as South Wall stripping progressed and access to Stage II ore
was advanced. Total material movement increased substantially, with 906,604 tonnes blasted during Q2 FY2026,
compared to the previous record of 603,309 tonnes in Q3 FY2025. Of this, 777,873 tonnes of material was extracted,
supporting continued access development and pit reconfiguration, with 721,290 tonnes of waste moved, up significantly
from the prior quarter.
Stripping progress and ramp construction advanced access to key ore zones with first access to the higher-grade Iolanthe
vein on track in Q3 FY2026. The strip ratio increased to 12.7:1, reflecting the deliberate prioritisation of waste removal to
unlock consistent, higher-quality ore supply into Stage II.
Mining productivity improved progressively with multiple successful blasts completed across priority areas, with ongoing
ramp development supporting safer access and improved material flow. As at quarter end, operational momentum
continued to build, with mining operations expected to reach the ore zone in the Iolanthe ore body in the following quarter,
positioning the site for higher ore delivery in volume and grade into the second half of FY2026.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 7
Above: Mining operations advancing on the South Wall, with drilled blast holes on the 345-335 RL level
Processing
Processing performance strengthened in line with increased mining activity and improved feed availability. During Q2
FY2026, Mt Carbine achieved an increase of quarterly material crushed to 157,965 tonnes, up from 115,509 tonnes in Q1
FY2026, supported by improved crushing availability and maintenance execution. Gravity Plant feed increased to 64,278
tonnes, from 46,905 tonnes in Q1FY2026, reflecting higher feed availability and improved plant utilisation.
Plant recoveries remained broadly stable at 73% (Q1 FY2026: 74%), slightly lower than historical levels due to reduced
feed grade. Average head grade into the gravity plant was 0.126% WO₃ (Q1 FY2026: 0.133%), driven primarily by normal
quarter-to-quarter variability in the Low-Grade Stockpile (LGSP) feed. Ore sourced from the pit during the period was of a
similar grade profile to LGSP material, reflecting the thin-vein nature of the mineralisation being mined at the current level.
As stripping continues and access improves into Stage II ore zones, head grade is expected to improve progressively in
line with the mine sequence.
Processing operations were intermittently impacted by equipment downtime, including screen bearing failures, crusher
maintenance and gravity circuit interruptions. Targeted maintenance and corrective works were completed across
crushers, screens, jigs and pumps, while wet crushing preparations advanced with new pumps, pipelines and cyclone
installations nearing completion. These upgrades are expected to materially improve throughput stability and recovery
consistency in subsequent quarters.
Concentrate production increased materially, with 5,884 mtu produced during Q2 FY2026, up from 4,610 mtu in Q1
FY2026. This improvement reflects higher ore throughput and improved operating continuity through the latter part of the
quarter.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 8
FUNDING
Equity Raising and Balance Sheet Strengthening
In Q2 FY2026, EQR completed a A$34 million equity raising (before costs) through the issue of 680 million new fully paid
ordinary shares at an issue price of A$0.05 per share.
In addition,
Funds managed by Oaktree Capital Management agreed to convert the remaining A$7.25 million balance of their
pre-royalty loan into equity at the same issue price (subject to shareholder approval).
In addition, CRONIMET converted US$3 million of its offtake advance loan to equity during the quarter.
Proceeds from the equity raising were allocated to a combination of balance sheet strengthening and growth initiatives,
including:
Repayment of A$7.0 million in outstanding trade payables
Repayment of A$4.2 million in convertible notes
Repayment of A$1.7 million in outstanding payments to Cronimet pertaining to the Mt Carbine JV buy-out in July
2024.
Advancement of mining activities at Mt Carbine to accelerate access to the high-grade Iolanthe Vein; and
Strengthening of general working capital to support higher sustained operating rates.
ASX Announcement 5 December 2025: ‘EQR Successfully Undertakes A$34 Million Equity Raising’
Refinancing of Spanish Debt and Offtake Financing
During the quarter, the Company entered a binding term sheet for a €15 million, three-year prepayment facility with Traxys
Europe S.A., to be repaid via set-off against monthly deliveries of tungsten concentrate. The facility carries an interest rate
of EURIBOR plus 5.5% and includes a six-month principal repayment grace period.
The prepayment facility is accompanied by agreed commercial terms for a five-year, index-priced offtake arrangement
covering a minimum of 3,500 tonnes of WO₃ contained in concentrate, providing long-term sales certainty and aligning
financing with production. Execution of definitive agreements and first drawdown remain subject to standard conditions
precedent. ASX Announcement 9 December 2025: ‘EQR Enters Into Binding Term Sheet For A EUR15 Million Prepayment
Facility’
Collectively, the equity raising and refinancing initiatives materially reduced near-term debt maturities, strengthened
liquidity and positioned the Company to fund increased mining rates, plant optimisation and expansion activities across its
Australian and Spanish operations. EQR enters the second half of FY2026 with an improved capital structure, enhanced
funding certainty and increased exposure to a favourable tungsten pricing environment.
Tungsten Markets
Global tungsten markets continued to demonstrate strong price momentum through Q2 FY2026, underpinned by tight
upstream supply, constrained APT output and ongoing structural supply-demand imbalances. In China, domestic long-
term contract prices for key products, including Ammonium Paratungstate (APT) and concentrate, have advanced
materially year-on-year, with APT prices rising sharply and remaining elevated relative to 2024 levels. Recent data shows
APT and tungsten concentrate prices sustaining significant gains, reflecting limited spot availability and strong inventory
discipline among producers. European APT CIF prices also strengthened during the quarter, supported by tight import
availability and pre-holiday production curbs, with market talk of APT offers approaching US$850–$1,000/mtu in certain
trades. Overall, the market remains supported by supply constraints and ongoing shortages reported by downstream
customers, and broader sentiment pointing to continued price strength into early 2026.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 9
Above: 12 Month History of APT Low-Price. Price as of 2 January 2026. Source: Fastmarkets. Tungsten APT
88.5% WO3 (min), CIF Rotterdam and Baltimore, duty-free, $/mtu WO3
Quarterly Cashflow Report
Cash Flows from Operating Activities
In Q2 FY2026, net cash generated from operating activities for the Group amounted to A$1.15 million. This includes the
costs incurred to accelerate the South-West Wall cutback at Mt Carbine to access the high-grade Iolanthe Vein in Q3
FY2026. Of note:
Barruecopardo generated positive operating cashflows of approximately A$14.2 million driven by a 33% increase in
production, an increase in the APT price and the benefits of making prepayments to contractors in Q1 FY2026 (these
arrangements have now ceased enabling a steadier total cash production cost moving forward).
300
400
500
600
700
800
900
1000
APT
Low
Price
($US/mtu)
12 months - APT Low Price (CIF EU/US) $US / mtu
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 10
Overall Mt Carbine generated negative operating cashflows of approximately A$ 10.9 million in the quarter as it
continues to accelerate the South Wall cut back.
Corporate overheads for the quarter were A$ 1.9 million driven by salaries and service provider costs supporting the
refinancing of the Company.
Cash Flows from Investing Activities
In Q2 FY2026, net cash used in investing activities totalled A$2.66 million including payments made for the TOMRA ore
sorter to be used in the Mt Carbine expansion project.
Cash Flows from Financing Activities
In Q2 FY2026, net cash from financing activities totalled A$12 million. This primarily consisted of A$34 million (before fees)
from Equity Placements and the exercise of options used to reduce debt by A$20m (incl A$1.6m of finance lease
payments).
Cash and Financing Facilities
As of 31 December 2025, the Company held cash of A$21.98 million, an increase from A$11.47 million in cash held as at
30 September 2025. Spanish loan facilities in Euros headroom of A$3.17 million available at quarter end.
SUSTAINABILITY & SOCIAL PROGRAMS
For more information on the Company’s ESG commitments and ongoing initiatives, please visit EQR’s LinkedIn, Saloro’s
LinkedIn and the Sustainability page on EQR’s Website.
EXPLORATION ACTIVITIES / RESERVES AND RESOURCES
Wolfram Camp
Exploration activities at Wolfram Camp were limited during the quarter due to seasonal wet-season conditions restricting
site access. Planning and preparatory work continued during this period, with on-ground programs scheduled to
recommence during the dry season. Further updates on exploration activities and progress will be provided as work
programs advance.
Mineral Resource and Ore Reserves
There has been no material change to the Company's Mineral Resources and Ore Reserves since the last publication. For
the latest information, please refer to:
- Mt Carbine & Barruecopardo (Life Of Mine & production target clarification): ASX Announcement 12 December
2025: “Clarification of Production Targets and Life of Mine Plans”.
- Mt Carbine Mine: EQR Annual Report FY2025
- Barruecopardo Mine: ASX Announcement 22 October 2025: “EQ Resources Barruecopardo Mine Increases Ore
Reserves by 39%”.
Tenements
There have been changes to the tenement holdings of the Company and its controlled entities. The current tenement
interests are disclosed below in accordance with ASX Listing Rule 5.3.3.
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 11
Australia
Note:
- EPM 14871 & EPM 14872 Renewal lodged, pending registration.
Spain
Location Holding Entity
Beneficial
Interest
Interest
Acquired or
Disposed
Area Expiry date
Queensland, Australia
ML 4867 Mt Carbine Quarries Pty Ltd 100% N/A 358.5 ha 31/07/2041
ML 4919 Mt Carbine Quarries Pty Ltd 100% N/A 7.891 ha 31/08/2041
EPM 14871 EQ Resources Limited 100% N/A 10 sub-blocks 12/12/2025
EPM 14872 EQ Resources Limited 100% N/A 21 sub-blocks 11/12/2025
EPM 28898 EQ Resources Limited 100% 17/06/2024 147 sub-blocks 17/06/2029
ML = Mining Lease; EPM = Exploration Permit for Mineral (Qld); EL = Exploration License (NSW)
Location Holding Entity
Beneficial
Interest
Interest
Acquired
Area Expiry date Granting
Salamanca, Spain
C.E. Barruecopardo, 6.432-10 Saloro, SLU 100% 18/01/2024 2,100 Ha 1/11/2041 20/11/2014
P.I. Saldeana 1
a
Fracción, 6.432-11 Saloro, SLU 100% 18/01/2024 13 Aug.* 13/08/2001
P.I. Saldeana 2
a
Fracción, 6.432-12 Saloro, SLU 100% 18/01/2024 13 Aug.* 13/08/2001
P.I. Milano, 6.432-20 Saloro, SLU 100% 18/01/2024 29,000 Ha 13 Aug.* 13/08/2011
P.I. Cortegana, 6.570 Saloro, SLU 100% 18/01/2024 16,700 Ha 14 Nov.* 14/11/2006
P.I. Almonaster, 6.572 Saloro, SLU 100% 18/01/2024 4,300 Ha 14 Nov.* 14/11/2006
P.I. Aracena, 6.649 Saloro, SLU 100% 18/01/2024 5,300 Ha 30 Oct.* 30/10/2008
P.I. Brincones, 6.834 Saloro, SLU 100% 18/01/2024 6,100 Ha 7 May* 7/05/2013
C.E. = Mining Lease; *P.I. = Exploration Permit w hich is renew ed annually.
29,300 Ha
resourcing the new economy for a better tomorrow
Quarterly Activities Report - Quarter ended 31 December 2025 Page 12
Released on the authority of the Board by: Further Enquiries:
Craig Bradshaw Peter Taylor
Managing Director Investor Relations
M: 0412 036 231
E: peter@nwrcommunications.com.au
About EQ Resources Limited
EQ Resources Limited is a leading global tungsten mining company dedicated to sustainable mining and processing
practices. The Company is listed on the Australian Securities Exchange, with a focus on expanding its world-class tungsten
assets at Mt Carbine in North Queensland (Australia) and at Barruecopardo in the Salamanca Province (Spain). The
Company leverages advanced minerals processing technology and unexploited resources across multiple jurisdictions,
with the aim of being a globally leading supplier of the critical mineral, tungsten. The Company aims to create shareholder
value through the exploration and development of its current project portfolio whilst continuing to evaluate corporate and
exploration opportunities within the new economy and critical minerals sector globally.
Forward-looking Statements
This announcement may contain forward-looking statements. Forward-looking statements address future events and
conditions and, therefore, involve inherent risks and uncertainties. Actual results may differ materially from those currently
anticipated in such statements. Particular risks applicable to this announcement include risks associated with planned
production, including the ability of the Company to achieve its targeted production outline due to regulatory, technical or
economic factors. In addition, there are risks associated with estimates of resources, and there is no guarantee that a
resource will have demonstrated economic viability as necessary to be classified as a reserve. There is no guarantee that
additional exploration work will result in significant increases in resource estimates. Neither the Australian Securities
Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Australian Securities Exchange)
accepts responsibility for the adequacy or accuracy of this announcement.
Follow us:
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
EQ RESOURCES LIMITED
ABN Quarter ended (“current quarter”)
77 115 009 106 31 December 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
1. Cash flows from operating activities
21,836 36,489
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development (1) (6)
(c) production (9,497) (31,942)
(d) staff costs (7,885) (16,000)
(e) administration and corporate costs (1,202) (2,447)
1.3 Dividends received (see note 3) - -
1.4 Interest received 69 83
1.5 Interest and other costs of finance paid (2,467) (3,233)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other
- Diesel Fuel Tax Credits
- Grants
- Traineeship Subsidies
- Other
301
-
-
-
549
-
4
-
1.9 Net cash from / (used in) operating
activities
1,154 (16,503)
2. Cash flows from investing activities
(47) (1,359)
2.1 Payments to acquire or for:
(a) entities
(b) tenements - 3
(c) property, plant and equipment (2,331) (3,961)
(d) exploration & evaluation (if capitalised) (23) (24)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
(e) investments - -
(f) other non-current assets - -
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - 6
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
- ERC Increase & Security Deposits (255) (255)
2.6 Net cash from / (used in) investing
activities
(2,656) (5,590)
3. Cash flows from financing activities
33,500 55,748
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options 683 683
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(2,3