Half Year Financial Report
Released
Released
Announcement PDF
HALF YEAR REPORT
DECEMBER 2024
EQ RESOURCES LIMITED
ABN 77 115 009 106
DECEMBER 2024
i
CORPORATE DIRECTORY
Directors
Oliver Kleinhempel
Non-executive Chairman
Stephen Layton
Non-executive Director
Richard Morrow
Non-executive Director
Stephen Weir
Non-executive Director
Zhui Pei Yeo
Non-executive Director
Company Secretary
Melanie Leydin
Principal Place of Business
6888 Mulligan Highway
Mount Carbine QLD 4871
Share Register
Automic Pty Ltd
Level 5 126 Philip Street
Sydney NSW 2000
T +61 (0)2 9698 5414
Auditors
Nexia Melbourne Audit Pty Ltd
Level 35, 600 Bourke Street
Melbourne VIC 3000
T +61 (0)3 8613 8888
Registered Office
F +61 (0)3 8613 8800
Level 4, 100 Albert Road
South Melbourne VIC 3205
Stock Exchange Listing
T +61 (0)7 4094 3072
Listed on the Australian Securities Exchange (ASX)
W www.eqresources.com.au
ASX Code: EQR
E info@eqresources.com.au
ACN: 115 009 106
ABN: 77 115 009 106
1
i
CONTENTS
OPERATING & FINANCIAL REVIEW................................................................................. 1
EQR GROUP HALF YEAR FY2025 – PRODUCTION SUMMARY ..................................................................2
HEALTH AND SAFETY .....................................................................................................................................3
Mt Carbine ..........................................................................................................................................................3
Saloro..................................................................................................................................................................3
MT CARBINE OPERATIONS ............................................................................................................................4
Open Cut Mining .................................................................................................................................................4
Processing ..........................................................................................................................................................8
Quarry Operations ............................................................................................................................................10
SALORO / BARRUECOPARDO .....................................................................................................................11
Open Cut Mining ...............................................................................................................................................11
Processing ........................................................................................................................................................14
FINANCIAL AND CORPORATE .....................................................................................................................18
Tungsten Markets .............................................................................................................................................20
SUSTAINABILITY ............................................................................................................................................22
EXPLORATION ACTIVITIES, RESERVES, AND RESOURCES ...................................................................24
Wolfram Camp ..................................................................................................................................................24
Mineral Resources & Ore Reserves Estimates ................................................................................................25
EQ Resources Tenement Interests ..................................................................................................................26
FINANCIALS ..................................................................................................................... 27
DIRECTORS’ REPORT ....................................................................................................................................28
Directors............................................................................................................................................................28
Operating Results .............................................................................................................................................28
Review of Operations .......................................................................................................................................28
Auditor’s Independence Declaration .................................................................................................................28
CONSOLIDATED STATEMENT OF PROFIT OR LOSS AND OTHER COMPREHENSIVE INCOME .........29
CONSOLIDATED STATEMENT OF FINANCIAL POSITION .........................................................................30
CONSOLIDATED STATEMENT OF CASH FLOWS ......................................................................................31
CONSOLIDATED STATEMENT OF CHANGES IN EQUITY..........................................................................32
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS ...................................................................33
1.
SUMMARY OF MATERIAL ACCOUNTING INFORMATION ......................................................33
2.
REVENUE AND OTHER INCOME ..............................................................................................35
3.
ACQUISTION OF SUBSIDIARIES...............................................................................................35
4.
FAIR VALUE REVALUATION OF FINANCIAL LIABILITIES .......................................................36
5.
INVENTORY ................................................................................................................................36
6.
FINANCIAL ASSETS ...................................................................................................................37
7.
TRADE AND OTHER RECEIVABLES .........................................................................................37
8.
RECEIVABLES ............................................................................................................................38
9.
DEFERRED EXPLORATION AND EVALUATION EXPENDITURE ...........................................38
10.
EMPLOYEE BENEFITS ...............................................................................................................39
11.
TRADE AND OTHER PAYABLES ...............................................................................................39
1
ii
12.
13.
14.
15.
16.
17.
18.
19.
20.
ISSUED CAPITAL ........................................................................................................................39
CONVERTIBLE NOTES ..............................................................................................................40
CONTINGENT LIABILITIES .........................................................................................................42
BORROWINGS ............................................................................................................................42
EQUIPMENT LEASES .................................................................................................................43
FINANCIAL LIABILITIES ..............................................................................................................43
NEW ACCOUNTING STANDARDS AND INTERPRETATIONS .................................................44
OPERATING SEGMENTS ...........................................................................................................44
SUBSEQUENT EVENTS .............................................................................................................45
DIRECTORS’ DECLARATION ........................................................................................................................46
AUDITOR’S INDEPENDENCE DECLARATION .............................................................................................47
INDEPENDENT AUDITOR’S REPORT ...........................................................................................................48
FORWARD LOOKING STATEMENTS ............................................................................................................50
2
resourcing the new economy for a better tomorrow
OPERATING &
FINANCIAL REVIEW
1
resourcing the new economy for a better tomorrow
EQR Group Half Year FY2025 – Production Summary
Operations
Mt Carbine
Saloro
EQR Group
Unit
H2 FY24
H1 FY25
H2 FY24
H1 FY25
H2 FY24
H1 FY25
Waste
kt
1,102
805
2,816
3,251
3,917
4,055
Ore
kt
292
318
594
760
886
1,078
Total Tonnes Mined
kt
1,394
1,123
3,409
4,011
4,803
5,134
Strip Ratio
W:O
3.8 : 1
2.5 : 1
4.7 : 1
4.3 : 1
4.4 : 1
3.8 : 1
Closing Ore Stock
kt
68
11
308
304
376
315
Gravity Plant Feed
kt
125
132
448
453
573
Gravity Plant Grade
%
0.412%
0.402%
WO3 Produced*
mtus
38,224
35,071
584
-
46,352
61,214
84,576
96,285
*Note: Metric Tonnes Unit, 1 mtu = 10kg WO3
The end of the First Half of the Financial Year 2025 that ended 31 December 2024 (H1 FY2025), marked a
period of strong production growth across Mt Carbine and Barruecopardo, driven by higher material movement,
increased ore processing, and efficiency improvements.
At Mt Carbine, 1.12 million tonnes of material were mined, including 318,292 tonnes of ore, while 433,753
tonnes were crushed, with 331,424 tonnes from the Open Pit and 102,329 tonnes from the Low-Grade
Stockpile (LGSP). The XRT Ore Sorter throughput increased by 18%, contributing to higher feed grades at the
Gravity Plant, which set new processing records in Q1 FY2025, producing 26,028 mtu of concentrate, though
low water levels in Q2 impacted production.
Meanwhile, Saloro Operations at the Barruecopardo Mine saw over 4 million tonnes of material extracted (3.2
million tonnes of waste, 760,107 tonnes of ore), reflecting a 17.6% increase from H2 FY2024, while processing
volumes surged, with 699,156 tonnes crushed and 452,739 tonnes fed into the Gravity Plant. XRT Ore Sorter
product yield increased by 422%, supporting record recovery rates consistently above 60%. With higher-grade
ore access expected in H2 FY2025, production is set to further strengthen. H1 FY2025 has demonstrated that
the positive changes initiated since the Saloro operation’s acquisition in January 2024 are poised to maintain
a solid trajectory of strong operational performance and favourable results driven by continuous optimisation
and improvements.
The consolidated EQR Group produced 96,285 mtu of tungsten concentrate (Mt Carbine 35,071 mtu; Saloro
61,214 mtu), and 5.13 million total tonnes mined (Mt Carbine 1.12 million tonnes; Saloro 4.0 million tonnes),
reflecting a nearly 14% increase in total mtus produced and a 7% increase in tonnes mined compared to the
previous Half Financial Year (H2 FY2024).
2
resourcing the new economy for a better tomorrow
Health and Safety
Mt Carbine
Following the transition to an Owner-Operator model for mining operations at Mt Carbine, combined with the
move from 12-hour to 24-hour mining activities, both staff numbers and overall man-hours worked have risen.
Despite this increased workforce, Mt Carbine’s total recordable injuries (TRIs) remained the same at 9
occurrences for H1 FY2025. The Total Recordable Injury Frequency Rate (TRIFR) for end of H1 FY2025 was
74. The Mt Carbine Operations recorded several positive safety indicators during the quarter, including 7,132
“Take 5s” vs 3,483 in H2 FY2024, more frequent workplace inspections and safety meetings. Additionally,
more Job Safety Environment Analysis were conducted.
New automated breathalysers were installed on site and regular drug testing campaigns were conducted.
Employees at Mt Carbine are all locals from the Cairns – Mossman - Mareeba region and encouraged to upskill
and strengthen their competencies. During this period, several groups received specialised safety training
including Working at Heights, Confined Space Entry, supervisory training, and diverse range of first aid courses
(including CPR and Advanced First Aid).
Saloro
The Saloro Operations 37 employees attended training courses including mining risk and mobile machinery.
Saloro operations also implemented 30 new safety improvements.
Total recordable incidents (TRI) have dropped significantly from 16 for the calendar year ended 31 December
2023 (CY 2023) to a total of 9 for CY 2024, reflecting the impact of robust safety initiatives and cross-company
collaboration of best practices initiatives and a strengthening of the Company’s overall safety culture.
The Saloro team continues to conduct regular safety training sessions to reinforce proper procedures,
focussed particularly on the importance of equipment isolation during maintenance. The introduction of the
‘Step Back Take 5’ Job Safety Environment Analysis (JSEA) early H1 FY2025 has been particularly impactful,
with employees increasingly adopting it as a routine practice. This initiative is becoming ingrained in the
workplace culture, thanks to continued procedural reviews, improved monitoring, and proactive engagement
with staff.
3
resourcing the new economy for a better tomorrow
Mt Carbine Operations
Pictured: The Andy White Open Pit at Mt Carbine end January 2025, mining operations entered the Stage II
Open Pit and focused on stripping waste in cutback area.
Open Cut Mining
In August 2024, after 14 months of contractor mining, the Company announced its transition to owner-operator
mining at the Mt Carbine mine (See ASX Announcement: ‘Mt Carbine Mine Transition to Owner-Operator
Mining’ dated 16th August 2024). The Operational team has since established baseline costs and new
procedures, resulting in cost savings, enhanced operational control, improved mining flexibility, and upskilling
of the local workforce. It also involved bringing key management and the bulk of the contractor workforce into
the Mt Carbine operations, maintaining continuity and leveraging their expertise.
All new fleet equipment was successfully commissioned promptly, including a CAT 90-tonne excavator, two
60-tonnes Volvo dump trucks, a CAT 745 Moxy water truck, and two bulldozers. This expanded fleet, coupled
with round-the-clock operations, has already shown strong outcomes. In the first part of H1FY2025, mining
continued in Open Pit Stage I at the 285m RL level, while stripping for Stage II advanced between 365m and
345m Reduced Level (“RL”), revealing initial signs of the Johnson, Wayback, and Iolanthe vein systems.
4
resourcing the new economy for a better tomorrow
Pictured: Left, the new 90T CAT 395 Excavator on its first day; Right, one of the new 60t Volvo Articulated
Dump Truck, part of the new fleet.
By the close of Q1 FY2025, Mt Carbine had fully switched to a 24-hour mining roster, boosting monthly
tonnage, reducing unit costs. Building on this momentum, Q2 FY2025 marked the first full quarter under the
owner-operator model and the mining team extracted 572,905 tonnes of material—a 4% increase over the
previous quarter and 15% higher than Q2 FY2024. A new mining schedule was introduced shortly after the
transition, with a priority changed to kickstarting the Stage II Pit with the planned waste stripping and a
modification of the blast sequence, allowing earlier access to higher-grade veins. Previous mining schedules
included several small blasts at the bottom of the Stage I pit until the end of H1 FY2025, but management
determined it would be more cost-effective to recover those deeper ore bodies once the pit is widened and
under drier conditions.
Pictured: The Southeast corner of the Open Pit, initial focus of the Stage II pit stripping and cut back with the
Iolanthe and Bluff vein package as main targets with drilling progressing at 345-335 RL.
5
resourcing the new economy for a better tomorrow
The waste stripping on upper levels in the pit’s south-east section 355m RL–345m RL advanced well, with the
upper portion of the ore body reached in January 2025 in the level 345-335 RL as seen above. The upcoming
325m RL level will be accessed in H2 FY2025 and is expected to yield a significant grade increase, as indicated
by extensive RC drilling in 2024 and January 2025 (See RC Drilling Section below).
Mt Carbine also switched to its own drilling operations and two Sandvik drill rigs were mobilised. With drilling
operations shifted in-house, new staff with specialised skills have been successfully integrated into the team.
Blasting is now managed by a newly appointed contractor to further optimise costs.
Meanwhile, the Terex Finlay 893 Scalper continues processing the historic LGSP in parallel, which is then
upgraded through the Ore Sorter plant to maintain a steady feed for the Gravity Plant whenever stripping
activities temporarily reduce ore deliveries.
In H1 FY2025, 15 blasts were conducted, 1.12 million tonnes of material were extracted with 318,292 tonnes
of ore and 805,000 tonnes of waste for a strip ratio of 2.5 : 1. Since the Open Pit’s reopening, a total of 2.43
million tonnes of waste have been stripped.
Pictured: The new Sandvik drill rigs arriving at MtCarbine on commission day.
Mt Carbine RC drilling campaign
In early H1 FY2025, the Company completed 37 additional infill Reverse Circulation (RC) drill holes, totalling
1,437 meters, targeting the main Ore Bodies of the Stage II Pit. Drilled from the current pit floor at
approximately 295–305 meters RL, these holes delineated four principal zones of mineralisation spanning a
100-meter strike length and an 80-meter width. This area forms part of an extensive main vein system
stretching 1.2 kilometres along strike, which also includes the parallel Iron Duke Vein system to the north. Both
systems are believed to continue further west, and this confirmed continuity is expected to significantly
contribute to the Company’s underground ore body.
6
resourcing the new economy for a better tomorrow
Pictured: Orthomosaic image of the Pit I floor showing drill location for the 37 holes completed in July 2024.
Building on these outcomes, the Company wrapped up its Eastern Cut Back RC drilling campaign in December
2024, totalling another 28 drill holes (741 meters) from the higher up 345-meter RL bench. This aimed to
identify the emergence of main ore loads in the Eastern Cut Back Program, supported by a 1.2-million-tonne
waste stripping initiative between October and December 2024. These efforts enabled early access to the
main ore body at the Andy White Open Cut during Stage II. Drilling targeted three key zones—the Dazzler,
Johnson, and Iolanthe ore bodies and confirmed significant high-grade mineralisation at the 345-meter bench,
marking the top of the Iolanthe ore body. Initial blasts in H2FY2025 are expected to provide enhanced volumes
of high-grade ore from this zone.
Pictured: The location of the drilling campaign in December 2024 with an outline of the main vein
packages targeted in Stage II with the ore blocks in red.
7
resourcing the new economy for a better tomorrow
The decision to prioritise stripping in the mine’s eastern section has proven advantageous, with increased ore
availability now realised as the operation enters the primary ore zone. Although stripping can be challenging,
the benefits are becoming evident. Looking ahead, EQR remains focused on fully exploring the potential of the
Mt Carbine tungsten deposit to ensure long-term resource stability and to reinforce its position as a leading
tungsten producer.
Pictured: Block model showing main high grade ore body relative to Open Pit Stage I (In white,
currently mined) and Open Pit Stage II (in blue, next stage that has started)
For more information on the RC drilling campaigns of 2024:
−
ASX Announcement 30th April 2024: ‘Mt Carbine Infill Drilling Reveals High Garde Zones in Stage II
Pit’
−
ASX Announcement 3rd June 2024: ‘Mt Carbine Infill Drilling Reveals Additional High-Grade Ore In
Stage II Waste Cutback Area’
−
ASX Announcement 29th July 2024: ‘High-Grade Drilling Results Confirm Main Mineralised Level at
MtCarbine’,
−
ASX Announcement 28th January 2025: ‘Results of the Eastern Cutback RC Drilling Campaign’
Processing
In H1 FY2025, a total of 433,753 tonnes of ore were crushed, comprising 331,424 tonnes from the Open Pit
and 102,329 tonnes from the historic LGSP. The Gravity Plant feed increased from 125,093 tonnes to 131,524
tonnes while the lower feed grade and low water levels in Q2 impacted the concentrate production that
witnessed a small decrease with 35,071 mtus produced in H1 FY2025 from 38,224 mtus in H2 FY2024.
Q1 FY2025, has been a record quarter at Mt Carbine across all processing plants. 259,709 tonnes of ore have
been crushed, and 165,779 tonnes of crushed ore have been processed through the XRT Ore Sorters,
reflecting an 18% increase from the prior quarter. This rise in Sorter product is attributed to the newly
commissioned ejection system at Tomra XRT Ore Sorter #2 (completed in mid-June 2024), and combined with
a solid yield of over 10%, contributed to an increase of feed grade at the Gravity Plant from 0.438% WO3 for
Q4 FY2024 to 0.545% WO3 for Q1 FY2025.
8
resourcing the new economy for a better tomorrow
Pictured: XRT Ore Sorters at Mt Carbine: A key driver of efficiency and economic success, playing a crucial
role in maximising the economic viability of operations by optimising ore processing, increasing feed grades,
and reducing waste—ensuring sustainable and efficient production.
The Gravity Plant at Mt Carbine Mine recorded several new production records in the quarter with a new daily
record of 641 mtus in 24hrs; a new monthly record of 10,702 mtus in September; and achieved a quarterly
record of 26,028 mtu in Q1 FY2025. Improvements in concentrate production were due to:
-
Increased feed grade thanks to the additional Sorter Product processed
-
Increased recovery following the installation of the scavenger jig
-
Increased overall Plant feed volume from 60,197 tonnes to 70,284 tonnes
During Q2 FY2025, water levels in the dam remained low, with Mt Carbine receiving just 130mm of rain,
significantly lower than both the 808mm recorded in the same quarter of the previous year and the 10-year
area average of 250mm. Although this wet season’s rainfall was below expectations, EQR anticipates
substantial precipitation in the March quarter, given historical norms (636mm average). Should these rains
materialise, they are expected to replenish dam levels sufficiently to support operations for the remainder of
CY2025.
In response to the low water levels, the Crushing, Screening, and Ore Sorting operations shifted from wet to
dry processing in early November, prioritising water allocation to the Gravity Plant. Despite continued work on
raising the dam, inadequate rainfall forced the temporary shutdown of the Gravity Plant in December. The
focus thus shifted to mining operations and stripping, while crucial water recycling enhancements and
maintenance were undertaken across all plants.
Modest rainfall in early January allowed the Gravity Plant to restart in the second week of the month, with
stockpiled ore ensuring a multi-day feed buffer for potential maintenance or further interruptions. This initial
ore blend, sourced from the top level of the ore body and the LGSP, has a relatively modest grade; however,
higher-grade material from the next levels down should be accessed soon.
Looking ahead, plans are in place to double processing capacity in 2025. All equipment and supporting
structures for the new Sandvik Crushing and Screening Plant have arrived on site, and preparatory work for
assembly will commence shortly.
The strong ore grade from the 305 RL level in the Iolanthe vein package was a key factor in achieving the
September 2024 processing record. Recent RC drilling campaigns have validated the block model, reinforcing
9
resourcing the new economy for a better tomorrow
confidence in the resources. Combined with record production from processing ore blocks sourced from the
targeted main ore body, these results indicate a promising outlook for future production, particularly as mining
progresses deeper to the 325 RL level and beyond in H2 FY2025, where grades are expected to further
improve.
Quarry Operations
Quarry sales saw steady growth in Q1 FY2025 following a successful tender for disaster recovery work in the
aftermath of Tropical Cyclone Jasper. Ongoing bank retention remedial efforts throughout August and
September restored road access for local residents. During the quarter, Mt Carbine Quarry also submitted
multiple tenders and collaborated closely with local civil contractors, aiding additional recovery projects from
restoring access to local farms and cattle stations to rehabilitating key roads extending to the Daintree River.
This positive trajectory continued into Q2 FY2025, with quarry sales further strengthened by civil construction
firms rushing to complete projects ahead of the wet season. Mt Carbine Quarry maintained its close
partnerships with local companies and Councils, supporting ongoing disaster recovery initiatives. The
Company also awaits the outcome of a recently lodged Standing Offer Arrangement application with the
Department of Transport and Main Roads, covering the supply and delivery of quarry materials.
10
resourcing the new economy for a better tomorrow
Saloro / Barruecopardo
Open Cut Mining
In the first half of FY2025, operations at the Barruecopardo Mine focused on achieving production targets while
optimising efficiency and preparing for future pit development. Key initiatives included trialing 10-metre bench
blasting to improve cost-effectiveness, maximising water dam capacity through advanced evaporation
systems, and advancing the Phase 6 Open Pit development in the Northern Zone.
Operational Performance and Mine Development
Throughout H1 FY2025, significant material movement was achieved, with over 4 million tonnes of material
extracted, marking subsequent record quarter after quarter since EQR acquired the mine in January 2024.
This meant a 17.6% increase from H2FY2024 and included 3.2 million tonnes of waste and 760,107 tonnes of
ore, with production primarily focused on the central and southern areas of the pit between 590m RL and 575m
RL. The same area was also the site for successful 10-metre bench blasting trials, a key operational efficiency
project.
Drilling and Blasting on 10-Metre Benches
Traditionally, drilling and blasting at Barruecopardo were conducted on 5-metre benches due to the specific
characteristics of the mineralised zone. However, during H1 FY2025, five experimental blasts were carried out
on 10-metre benches to assess potential improvements in operational efficiency.
Pictured: A 10-metre bench face with the mineralised zones marked
11
resourcing the new economy for a better tomorrow
Pictured: Block model imported into the OREPRO 3D software confirming the field observations made
by geologists.
The results have been promising, particularly in the central zone of the ore body, where geological continuity
is more consistent. Key benefits observed include:
−
Reduced drilling costs due to fewer drill meters required.
−
Lower blasting costs, benefiting from economies of scale.
−
Potential improvements in highwall stability.
−
Enhanced blast fragmentation for more efficient ore handling.
−
Overall, these trials resulted in an estimated cost savings of AU$0.16 per tonne, supporting the
potential long-term adoption of 10-metre bench blasting.
Development of the Barruecopardo Open Pit – Phase 6 (Northern Zone)
Significant progress was made in the Northern Zone as part of the Phase 6 Open Pit expansion, which
commenced following the end of the Black Stork and Egyptian Vulture breeding season, two protected species
present at the site. Early works have progressed ahead of schedule, allowing the mining team to access
mineralised zones sooner than initially anticipated.
In the western area, the switchback was established at 700m RL to facilitate efficient haulage access. In the
northern and eastern areas, mining activities advanced from 730m RL down to 700m RL to expose additional
mineralised zones. The latest resource block model confirms that as mining operations progress to deeper
levels, ore grades are expected to increase, following the natural continuity of Barruecopardo mine’s sheeted
vein tungsten deposit.
12
resourcing the new economy for a better tomorrow
Pictured: The Northern Area will be the target of Phase 6, next phase of the Open Pit.
Pictured: The Northern Area of the open pit as of end of December 2024, Resources Block Model in Phase 6. Colours
represent the grade of the ore. Red for high grade (>0.15% WO 3). Orange for lower grade (0.07-0.15% WO3). Blue for
very low grade (0.055-0.07% WO3). The tungsten-bearing mineral deposit at Barruecopardo is composed of sheeted
veins, and the pit development is designed to follow the continuity of the ore body. As mining operations progress to the
lower levels, the ore grade is expected to increase.
Water Management and Efficiency Enhancements
Throughout H1 FY2025, operational efforts remained focused on maximising water dam capacity. Advanced
evaporation systems were implemented alongside capacity enhancement measures to ensure a sustainable
water supply for mining and processing operations. Despite currently low dam levels, these initiatives have
positioned the operation better than in previous years, providing sufficient buffer capacity to handle any
unexpected heavy rainfall events without risk of overflow or operational disruptions.
13
resourcing the new economy for a better tomorrow
Barruecopardo Mine Ore Reserve Update
In October 2024, EQR released an updated